AGL 38.02 Increased By ▲ 0.08 (0.21%)
AIRLINK 197.36 Increased By ▲ 3.45 (1.78%)
BOP 9.54 Increased By ▲ 0.22 (2.36%)
CNERGY 5.91 Increased By ▲ 0.07 (1.2%)
DCL 8.82 Increased By ▲ 0.14 (1.61%)
DFML 35.74 Decreased By ▼ -0.72 (-1.97%)
DGKC 96.86 Increased By ▲ 4.32 (4.67%)
FCCL 35.25 Increased By ▲ 1.28 (3.77%)
FFBL 88.94 Increased By ▲ 6.64 (8.07%)
FFL 13.17 Increased By ▲ 0.42 (3.29%)
HUBC 127.55 Increased By ▲ 6.94 (5.75%)
HUMNL 13.50 Decreased By ▼ -0.10 (-0.74%)
KEL 5.32 Increased By ▲ 0.10 (1.92%)
KOSM 7.00 Increased By ▲ 0.48 (7.36%)
MLCF 44.70 Increased By ▲ 2.59 (6.15%)
NBP 61.42 Increased By ▲ 1.61 (2.69%)
OGDC 214.67 Increased By ▲ 3.50 (1.66%)
PAEL 38.79 Increased By ▲ 1.21 (3.22%)
PIBTL 8.25 Increased By ▲ 0.18 (2.23%)
PPL 193.08 Increased By ▲ 2.76 (1.45%)
PRL 38.66 Increased By ▲ 0.49 (1.28%)
PTC 25.80 Increased By ▲ 2.35 (10.02%)
SEARL 103.60 Increased By ▲ 5.66 (5.78%)
TELE 8.30 Increased By ▲ 0.08 (0.97%)
TOMCL 35.00 Decreased By ▼ -0.03 (-0.09%)
TPLP 13.30 Decreased By ▼ -0.25 (-1.85%)
TREET 22.16 Decreased By ▼ -0.57 (-2.51%)
TRG 55.59 Increased By ▲ 2.72 (5.14%)
UNITY 32.97 Increased By ▲ 0.01 (0.03%)
WTL 1.60 Increased By ▲ 0.08 (5.26%)
BR100 11,727 Increased By 342.7 (3.01%)
BR30 36,377 Increased By 1165.1 (3.31%)
KSE100 109,513 Increased By 3238.2 (3.05%)
KSE30 34,513 Increased By 1160.1 (3.48%)

imageMIRPUR: Water and Power Development Authority (WAPDA) is going to enhance the power generation capacity of the Mangla Power House to 1,310 megawatt in the near future.

WAPDA Chairman Lt Gen (R) Muzammil Hussain said this during his visit to Mangla dam Thursday.

WAPDA is implementing 'Mangla Refurbishment Project' with an approved PC I, cost of Rs.52.224 billion, he added.

He further said that the project on its completion, will enhance generation capacity of the existing Mangla Hydel Power Station from 1000 megawatt (MW) to 1310 MW.

Referring to the Refurbishment Project of Mangla Hydel Power Station, he said that WAPDA has devised a two-pronged strategy for optimal utilization of hydropower resources.

Under the strategy, WAPDA is not only initiating new hydropower projects but also rehabilitating and upgrading its existing hydel power stations to maximize the ratio of environment friendly and low-cost hydel electricity in the national grid.

He directed the officers concerned to complete the project within the stipulated time frame.

The Chairman expressed satisfaction over the exemplary implementation of Mangla Watershed Management Project to reduce the rate of sedimentation flowing into Mangla reservoir, as a result of which, the life of Mangla Reservoir has increased significantly.

During the visit, the Chairman was briefed that consequent upon the completion of Mangla Dam Raising Project in 2011, Mangla Dam is now the largest water reservoir of the country with live storage capacity of 7.48 million acre feet (MAF).

It was further briefed that Mangla Refurbishment Project will be implemented in various phases, wherein the generating units of Mangla Hydel Power Station will be refurbished by closing down one tunnel (two generating units) at a time.

First two units will be refurbished by December 2018, the next two by December 2019 and the other two by December 2020.

Refurbishment of all the 10 generating units will be completed by the year 2024, he remarked.

Copyright APP (Associated Press of Pakistan), 2016