East Europe nuclear plans face many obstacles

21 Feb, 2008

East European countries have jumped on the global nuclear renaissance bandwagon, but numerous hurdles facing atomic power mean projects could be delayed and some even abandoned, analysts say.
Slovakia, Romania and Hungary plan to build new reactors or extend the life of existing ones, driven by growing energy needs at home and European Union (EU) targets to reduce greenhouse gas emissions.
For others like Bulgaria, nuclear power is seen as a way to become major electricity exporters again after being forced to shut down communist era reactors as a condition to join the EU. Lithuania on the other hand, hopes that a new plant which it plans together with Poland, Latvia and Estonia, will reduce energy dependence on Russia.
Unlike in western European countries, nuclear power provokes little public opposition in eastern Europe. But projects still face construction problems common to the industry worldwide and added uncertainty over political change at home. "We can expect some nuclear reactors to be built but not the numbers that are predicted," Frank Barnaby, consultant at the Oxford Research Group, said.
High capital costs, difficulties in convincing banks to loan the money needed to build them, and uncertainty about future political support are just some of the hurdles that could scupper nuclear projects.
Meanwhile, the few nuclear engineering firms in the world able to build the plants are already stretched with over 30 reactors under construction globally and about 90 more planned.
"Some companies in Germany have cancelled coal plant plans...they knew engineering companies couldn't deliver. It will be the same with nuclear," said Stephan Werthschulte, managing partner with consultants Accenture.
FINANCIAL WOES: Most of the projects in eastern Europe seek private partners, big western utilities in particular, to share costs and responsibility. But raising funds is still not easy.
Sources in the capital Sofia said Bulgaria received little interest in a tender to pick a lead manager to secure financing for its 2,000 megawatt plant of Belene, which the government says would cost 4 billion euros ($5.89 billion) but some officials put it at over 6 billion. "Banks are hesitant. They want to see a partner who could safely run the reactors at high capacity to ensure that the huge costs could be covered," said one source familiar with Belene.
"If a country like Finland finds it difficult to push ahead with a new plant, what about Bulgaria," he said. Finland's fifth nuclear power reactor, seen as a test for Europe's nuclear future, is two years behind schedule and 50 percent over budget.
Sofia has extended its deadline for picking a strategic investor for 49 percent of the plant until mid-200 due to political wrangling about how to run Belene, which coupled with funding woes could push the start date well beyond the planned 2013.