Installation work of 23 power transformers completed

21 Jul, 2011

IESCO has completed the installation work of 23 power transformers of different capacity at twenty grid stations of the region just in three month's record time.
All the projects were completed with the financial assistance of Asian Development Bank. IESCO is sole company in all DISCO'S which completed the said projects before the target date. ADB has appreciated IESCO's marvellous performance on completion of the work just in three months. Due to the completion of the projects, the consumers would not only get smooth electricity, but would also get the facility of new electricity connections easily. While the complaints of low voltage and tripping would also be solved.
The projects including 13 Nos of 40MVA and 10 Nos of 26MVA power transformers while 18 Nos (incoming panel) of 11KV switch gear and 53 Nos (outgoing panel) of 11KV switch gear projects were completed with the cost of billions of the rupees to keep the voltage smooth.-PR

Read Comments