LAHORE: The Lahore Electric Supply Company (Lesco) has energized 50 new feeders to overcome the issues of low voltage and tripping during the month of Ramazan, said Chief Executive Officer (CEO) Ch Muhammad Amin.
According to him, 2307 kilometer long transmission line has been repaired at 132KV system while patrolling of 1091 kilometer transmission line has been carried out by the field staff. Besides, he said, felling of trees, replacement of transformers and 11kV lighting arresters, battery banks, faulty disk isolators, relays, jumpers, repairing of conductors and replacement, washing of disk isolators are a few more steps to ensure uninterrupted power supply to consumers during Ramazan.
Copyright Business Recorder, 2022