Neelum Jhelum project to go into full operation this season

06 Jan, 2019

Neelum Jhelum Hydropower Project is bracing up for full generation during the next high flow season that will start from April onwards. The project, after its commissioning, has been in operation for almost 8 months.
The project is now due for a thorough inspection of the electro-mechanical equipments in accordance with the contractual obligations. The said inspection will be carried out by the consultants and contractor of the project. The low water flow season has been chosen for carrying out the thorough inspection.
Neelum Jhelum Hydropower Project went into operation with commissioning of its first unit on April 13, 2018. All the four units of the project went into operation successfully in a phased manner by August 14, 2018. Since its commissioning, the project has so far injected over 1.8 billion units (kWh) to the National Grid.