ISLAMABAD: The World Bank “Integrated Flood Resilience and Adaptation Project (IFRAP)” of worth $213 million is likely to be restructured to facilitate quick disbursements of project funds earmarked for resilient housing reconstruction, and restoration.
According to the official documents, IFRAP was signed on 3rd July 2023 aimed at reviving and enhancing the livelihoods of communities affected by the 2022 floods and strengthen adaptive capacity to future extreme flooding events.
Project has so far disbursed equivalent to $22.38 million, while the current closing date of the project is 31 December, 2028.
2022 floods: $10.9bn aid received against $30bn losses
The project focuses on restoring essential services including housing, WASH, transport, agriculture, and irrigation, while building a foundation for long-term flood resilience through strengthening institutions and information systems.
The project consists of six components, including a Contingent Emergency Response component, aimed at rehabilitation and resilience in response to flood damage, primarily in Balochistan.
The Ministry of Planning Development and Special Initiatives (MoPDSI) as the project implementing entity has established a Federal Project Management Unit (FPMU) based in Islamabad, whereas, most of the implementation is to take place in the province of Balochistan.
To ensure efficient and smooth implementation of the project, this restructuring proposes changes in the withdrawal categories in Section III of the Second Schedule to the Financing Agreement and revision in Disbursement and Financing Instruction Letter (DFIL) to allow for the opening of a Designated Account for Category 4 for Housing Reconstruction Unit (HRU) activities.
Inclusion of HRU under the IFRAP project will involve some changes which includes opening of a separate designated account which means that this change will need production of separate IUFR and annual financial statements.
Flood devastation: World Bank approves $213mn for Balochistan
A dedicated FMS is needed to oversee HRU’s FM function which will be a signatory to the DA and will get a login in for client connection for submitting the reports and perform documentation of expenditures. Project wide internal audit firm will also perform the IA activity of HRU and the Office of Auditor General will perform its statutory audit.
A dedicated implementation unit Housing Reconstruction Unit (HRU) has been established in Quetta as an extension to the Federal Project Management Unit for implementing Component 3 on housing reconstruction and restoration. The HRU is responsible for managing and monitoring the performance of implementing partners, whose selection is in the final stages.
The HRU will receive Damage Assessment and Verification (DAV) data collected by the implementing partners. The HRU will also carry out spot checks and monitor data collection not only of the DAV but also that of technical inspections for release of housing reconstruction subsidy grant tranches.
The HRU will open centralised bank accounts in commercial bank branches of the choices of beneficiaries to transfer housing reconstruction grants directly into individual beneficiaries’ bank accounts without involvement of any third party. This necessitates ring-fencing the financial management arrangement under this component to maintain separate and clean housing subsidy records as it is likely to involve over half a million small transactions.
The current DFIL restricts the opening of a separate designated account for the HRU, requiring all disbursements to be processed through the Federal Project Management Unit (FPMU) housed in the Ministry of Planning Development and Special Initiatives (MoPDSI). This arrangement may lead to inefficiencies and delays in fund disbursement due to the centralised nature of the financial management.
By amending the withdrawal categories and revising the DFIL, the HRU would have direct access to the funds, which would result in a more streamlined and responsive financial management system. This change would enable the HRU to operate more autonomously and respond more quickly to the needs of the project, thereby, enhancing the overall effectiveness and efficiency of Part-3’s implementation.
The proposed amendments would also align the financial management structure with the operational structure, as the HRU has been established to specifically handle the tasks under Part-3.
Copyright Business Recorder, 2024
Comments
Comments are closed.