CNG, fertilizer, non-zero rated industry: RLNG supply to remain suspended till February 17
The supply of RLNG by Sui Northern Gas Pipe Lines Limited to fertilizer, CNG and non zero rated industry will remain suspended till February 17. The company will restore the supply of RLNG to industry after resumption of RLNG supply from Engro terminal operator on February 17.
According to the spokesperson of the SNGPL Engro terminal (EETPL) is proceeding for scheduled maintenance as per its contract with SSGC w.e.f. 0800 hrs on 14th February to 2000 hrs on 16th February, 2019. This shut down was earlier planned to start on February 13 but was delayed due to late entry of PSO lng carrier into the Port Qasim owing to high winds position which is beyond the control of SNGPL.