AGL 40.00 No Change ▼ 0.00 (0%)
AIRLINK 129.00 Decreased By ▼ -0.53 (-0.41%)
BOP 6.76 Increased By ▲ 0.08 (1.2%)
CNERGY 4.50 Decreased By ▼ -0.13 (-2.81%)
DCL 8.70 Decreased By ▼ -0.24 (-2.68%)
DFML 41.00 Decreased By ▼ -0.69 (-1.66%)
DGKC 81.30 Decreased By ▼ -2.47 (-2.95%)
FCCL 32.68 Decreased By ▼ -0.09 (-0.27%)
FFBL 74.25 Decreased By ▼ -1.22 (-1.62%)
FFL 11.75 Increased By ▲ 0.28 (2.44%)
HUBC 110.03 Decreased By ▼ -0.52 (-0.47%)
HUMNL 13.80 Decreased By ▼ -0.76 (-5.22%)
KEL 5.29 Decreased By ▼ -0.10 (-1.86%)
KOSM 7.63 Decreased By ▼ -0.77 (-9.17%)
MLCF 38.35 Decreased By ▼ -1.44 (-3.62%)
NBP 63.70 Increased By ▲ 3.41 (5.66%)
OGDC 194.88 Decreased By ▼ -4.78 (-2.39%)
PAEL 25.75 Decreased By ▼ -0.90 (-3.38%)
PIBTL 7.37 Decreased By ▼ -0.29 (-3.79%)
PPL 155.74 Decreased By ▼ -2.18 (-1.38%)
PRL 25.70 Decreased By ▼ -1.03 (-3.85%)
PTC 17.56 Decreased By ▼ -0.90 (-4.88%)
SEARL 78.71 Decreased By ▼ -3.73 (-4.52%)
TELE 7.88 Decreased By ▼ -0.43 (-5.17%)
TOMCL 33.61 Decreased By ▼ -0.90 (-2.61%)
TPLP 8.41 Decreased By ▼ -0.65 (-7.17%)
TREET 16.26 Decreased By ▼ -1.21 (-6.93%)
TRG 58.60 Decreased By ▼ -2.72 (-4.44%)
UNITY 27.51 Increased By ▲ 0.08 (0.29%)
WTL 1.41 Increased By ▲ 0.03 (2.17%)
BR100 10,450 Increased By 43.4 (0.42%)
BR30 31,209 Decreased By -504.2 (-1.59%)
KSE100 97,798 Increased By 469.8 (0.48%)
KSE30 30,481 Increased By 288.3 (0.95%)
Pakistan

Dasu hydropower project to start electricity generation in 2024

All six units of the Stage-I with cumulative generation capacity of 2160-MW would be completed by early 2025.
Published February 17, 2020
  • All six units of the Stage-I with cumulative generation capacity of 2160-MW would be completed by early 2025.
  • The chairman said that the issue pertaining to rates of land needed for the project had been resolved following support of federal and Khyber-Pakhtunkhwa governments.
  • The chairman said that besides main civil works of Stage-I, the construction work on seven different contracts relating to infrastructure development in the area was also under way.

LAHORE: WAPDA Chairman Lt-Gen (Retd) Muzammil Hussain has said that construction work on Dasu Hydropower Project was gaining momentum and it will start electricity generation in the second half of the year 2024.

WAPDA spokesman said here on Monday that all six units of the Stage-I with cumulative generation capacity of 2160-MW would be completed by early 2025.

The chairman made the disclosure during his visit to the project site, while General Manager (Land Acquisition and Resettlement), General Manager and Project Director (Dasu Hydropower Project) and representatives of the consultants and contractors were also present.

The chairman said that the issue pertaining to rates of land needed for the project had been resolved following support of federal and Khyber-Pakhtunkhwa governments.

He also reviewed construction activities at the main access tunnel leading to the power house, the two diversion tunnels, project offices and colony.

The project management briefed the chairman of the progress on main civil and preparatory works in the project area.

He was also informed that the Khyber-Pakhtunkhwa government and the district administration had assured of completing the process of land acquisition by June this year.

The chairman said that besides main civil works of Stage-I, the construction work on seven different contracts relating to infrastructure development in the area was also under way.

These included construction of right bank access roads, relocation of Karakoram Highway, construction of 132-Kv transmission line and grid station to provide electricity from Duber Khwar Hydel Power Station to the site for implementing the project and adjacent areas, project colony and resettlement works, he added.

 