AGL 38.10 Decreased By ▼ -0.12 (-0.31%)
AIRLINK 133.06 Increased By ▲ 4.09 (3.17%)
BOP 8.77 Increased By ▲ 0.92 (11.72%)
CNERGY 4.70 Increased By ▲ 0.04 (0.86%)
DCL 8.65 Increased By ▲ 0.33 (3.97%)
DFML 39.90 Increased By ▲ 0.96 (2.47%)
DGKC 85.90 Increased By ▲ 3.96 (4.83%)
FCCL 35.15 Increased By ▲ 1.73 (5.18%)
FFBL 75.50 Decreased By ▼ -0.21 (-0.28%)
FFL 12.85 Increased By ▲ 0.03 (0.23%)
HUBC 109.80 Decreased By ▼ -0.56 (-0.51%)
HUMNL 14.11 Increased By ▲ 0.10 (0.71%)
KEL 5.44 Increased By ▲ 0.29 (5.63%)
KOSM 7.73 Increased By ▲ 0.06 (0.78%)
MLCF 41.25 Increased By ▲ 1.45 (3.64%)
NBP 69.40 Decreased By ▼ -2.92 (-4.04%)
OGDC 191.73 Increased By ▲ 3.44 (1.83%)
PAEL 26.45 Increased By ▲ 0.82 (3.2%)
PIBTL 7.42 Increased By ▲ 0.05 (0.68%)
PPL 161.10 Increased By ▲ 8.43 (5.52%)
PRL 26.30 Increased By ▲ 0.91 (3.58%)
PTC 19.47 Increased By ▲ 1.77 (10%)
SEARL 83.60 Increased By ▲ 1.18 (1.43%)
TELE 7.87 Increased By ▲ 0.28 (3.69%)
TOMCL 34.07 Increased By ▲ 1.50 (4.61%)
TPLP 8.61 Increased By ▲ 0.19 (2.26%)
TREET 17.20 Increased By ▲ 0.42 (2.5%)
TRG 60.40 Increased By ▲ 4.36 (7.78%)
UNITY 28.50 Decreased By ▼ -0.28 (-0.97%)
WTL 1.35 No Change ▼ 0.00 (0%)
BR100 10,767 Increased By 108.4 (1.02%)
BR30 32,116 Increased By 784.8 (2.5%)
KSE100 100,003 Increased By 734.1 (0.74%)
KSE30 31,145 Increased By 112.1 (0.36%)

imageISLAMABAD: The government has so far released Rs. 141.228 billion under its Public Sector Development Programme (PSDP) for various projects against the total allocations of Rs. 540 billion for the fiscal year 2013-14.

According to latest data of Ministry of Planning and Development, out of these allocations, Rs 25,862 million has been released for various projects of Pakistan Energy Commission, out of its total allocations of Rs. 52,300 million earmarked under PSDP for FY2013-14.

Similarly, a sum of Rs 19,614 million has been released to National Highway Authority out of total allocation of Rs 63,038.619 million for the current fiscal year.

Out of the total funds of Rs. 25,739.199 million allocated for the National Health Service Regulations and Coordination Division for the current year, the Planning Commission released Rs 10,504.797 million so far.

The Commission also released Rs.11,129 million for Railway Division out of its total allocations of Rs. 30,964.894 million whereas Rs 306 million has been released for National food Security and Research Division out of its total allocations of Rs.750 million for the year.

Am amount of Rs.7,396 million has been released for Higher Education Commission out of its total allocation of Rs. 18,490 million for the year 2013-14 whereas out of total allocations of Rs2,363.974 million earmarked for Law, Justice and Parliamentary Affairs Division, Rs. 489.401 million has been released so far.

According to the data, the commission released Rs. 20,299 million for WAPDA (Power) out of its total allocations of Rs. 51,543.425 million where as Rs14,569 million has been provided to WAPDA (Water Sector) out of its total allocations of Rs57,840.211 million.

An amount of Rs. 4,462 million has been released for Earthquake Reconstruction and Rehabilitation Authority (ERRA) out of its total allocations of Rs.10,000 million for the current year.

The commission also released Rs.895.613 million for cabinet division, Rs.17.913 for Climate Change Division and Rs.289.200 million for Commerce Division.

In addition, Rs. 179.526 has been released for Education and Training Division, Rs.2,128.718 for Finance Division, Rs.160.954 million for Industries Division, 1,197.812 for Interior Division and Rs.68.694 for Narcotics Control Division.

The Commission, released Rs.20 million for Petroleum and Natural Resources Division, Rs157.710 for Planning and Development Division, Rs.868.042 million for Science and Technology Research Division, Rs.77.864 for SUPARCO and Rs. 63 million for Textile Industry Division.

An amount of Rs.4,815.4 has been released for AJK (Block and other projects), Rs.4,456.2 million for Gilgit Baltistan (Block and other projects) where as Rs.8,571 million has been released for SAFRON/FATA.

The Planning Commission of Pakistan has been following a proper mechanism for the release of funds and accordingly funds are released as per given mechanism.

The commission releases 20 percent of funds in first quarter (July-September), 20 percent in second quarter (October-December), 30 percent third quarter(January-March) and 30 percent in fourth quarter (April-June).