AGL 40.01 Decreased By ▼ -0.20 (-0.5%)
AIRLINK 127.00 Decreased By ▼ -0.64 (-0.5%)
BOP 6.69 Increased By ▲ 0.02 (0.3%)
CNERGY 4.51 Increased By ▲ 0.06 (1.35%)
DCL 8.64 Decreased By ▼ -0.09 (-1.03%)
DFML 41.04 Decreased By ▼ -0.12 (-0.29%)
DGKC 85.61 Decreased By ▼ -0.50 (-0.58%)
FCCL 33.11 Increased By ▲ 0.55 (1.69%)
FFBL 66.10 Increased By ▲ 1.72 (2.67%)
FFL 11.55 Decreased By ▼ -0.06 (-0.52%)
HUBC 111.11 Decreased By ▼ -1.35 (-1.2%)
HUMNL 14.82 Increased By ▲ 0.01 (0.07%)
KEL 5.17 Increased By ▲ 0.13 (2.58%)
KOSM 7.66 Increased By ▲ 0.30 (4.08%)
MLCF 40.21 Decreased By ▼ -0.12 (-0.3%)
NBP 60.51 Decreased By ▼ -0.57 (-0.93%)
OGDC 194.10 Decreased By ▼ -0.08 (-0.04%)
PAEL 26.72 Decreased By ▼ -0.19 (-0.71%)
PIBTL 7.37 Increased By ▲ 0.09 (1.24%)
PPL 153.79 Increased By ▲ 1.11 (0.73%)
PRL 26.21 Decreased By ▼ -0.01 (-0.04%)
PTC 17.18 Increased By ▲ 1.04 (6.44%)
SEARL 85.60 Decreased By ▼ -0.10 (-0.12%)
TELE 7.57 Decreased By ▼ -0.10 (-1.3%)
TOMCL 34.39 Decreased By ▼ -2.08 (-5.7%)
TPLP 8.82 Increased By ▲ 0.03 (0.34%)
TREET 16.82 Decreased By ▼ -0.02 (-0.12%)
TRG 62.55 Decreased By ▼ -0.19 (-0.3%)
UNITY 27.29 Decreased By ▼ -0.91 (-3.23%)
WTL 1.30 Decreased By ▼ -0.04 (-2.99%)
BR100 10,112 Increased By 26 (0.26%)
BR30 31,188 Increased By 17.5 (0.06%)
KSE100 94,996 Increased By 232 (0.24%)
KSE30 29,481 Increased By 71 (0.24%)
Pakistan

Rs2.2bn approved for Chitral Hydel Power Station's capacity enhancement

ISLAMABAD: The government has approved a project worth Rs 2.
Published November 23, 2016

imageISLAMABAD: The government has approved a project worth Rs 2.2 billion to enhance capacity of Chitral Hydel Power Station from one Megawatt to five megawatt.

The capacity enhancement project had been approved by the Central Development Working Party (CDWP) in its recently held meeting, official sources in the ministry of planning, development and reforms here on Wednesday said.

The PC-I of the project had been submitted to the Ministry of Water and Power after the power demand in Chitral area increased and there was a dire need to upgrade the capacity of existing Hydel Power Station at Chitral.

The concept paper of the project was forwarded to Ministry of Planning, Development and Reforms on November 11, 2014 for approval.

The existing 1.0 MW Chitral Hydel Power Station was located on the right bank of Lutkho River, 5 Km upstream of Chitral City.

The Project was commissioned in 1975 by diverting the flows of Lutkho River through 3.72 Km long channel and installing two units of 200 KW and two units of 300 KW each.

The power generated from Chitral Hydel Power Station was supplied to Chitral City through 11 KV Transmission Line.

In the initial construction phase of Project, limited flows of Lutkho River were diverted to Power Channel for generation of 1 MW only.

However the river had abundant flows which could be utilized for Power Generation by constructing a small diversion weir, remodeling of power channel and fore bay and installation of new penstocks and additional units. It was estimated that the power could be enhanced up to five MW.

WAPDA had preliminary studies for the proposed up-gradation. Topographic Survey, Geological Mapping for weir Intake, Power Channel and Power House areas and drilling at weir and Power House area were carried out. Tender Design Report had been completed by Hydro Planning WAPDA in May, 2012.

The estimated cost of the project was US$ 15 million and completion time was three years.

Copyright APP (Associated Press of Pakistan), 2016