AGL 38.20 Increased By ▲ 0.05 (0.13%)
AIRLINK 129.30 Increased By ▲ 4.23 (3.38%)
BOP 7.85 Increased By ▲ 1.00 (14.6%)
CNERGY 4.66 Increased By ▲ 0.21 (4.72%)
DCL 8.35 Increased By ▲ 0.44 (5.56%)
DFML 38.86 Increased By ▲ 1.52 (4.07%)
DGKC 82.20 Increased By ▲ 4.43 (5.7%)
FCCL 33.64 Increased By ▲ 3.06 (10.01%)
FFBL 75.75 Increased By ▲ 6.89 (10.01%)
FFL 12.83 Increased By ▲ 0.97 (8.18%)
HUBC 110.72 Increased By ▲ 6.22 (5.95%)
HUMNL 14.03 Increased By ▲ 0.54 (4%)
KEL 5.22 Increased By ▲ 0.57 (12.26%)
KOSM 7.69 Increased By ▲ 0.52 (7.25%)
MLCF 40.08 Increased By ▲ 3.64 (9.99%)
NBP 72.51 Increased By ▲ 6.59 (10%)
OGDC 189.18 Increased By ▲ 9.65 (5.38%)
PAEL 25.74 Increased By ▲ 1.31 (5.36%)
PIBTL 7.38 Increased By ▲ 0.23 (3.22%)
PPL 153.45 Increased By ▲ 9.75 (6.78%)
PRL 25.52 Increased By ▲ 1.20 (4.93%)
PTC 17.92 Increased By ▲ 1.52 (9.27%)
SEARL 82.50 Increased By ▲ 3.93 (5%)
TELE 7.63 Increased By ▲ 0.41 (5.68%)
TOMCL 32.50 Increased By ▲ 0.53 (1.66%)
TPLP 8.48 Increased By ▲ 0.35 (4.31%)
TREET 16.74 Increased By ▲ 0.61 (3.78%)
TRG 56.01 Increased By ▲ 1.35 (2.47%)
UNITY 28.85 Increased By ▲ 1.35 (4.91%)
WTL 1.34 Increased By ▲ 0.05 (3.88%)
BR100 10,684 Increased By 595 (5.9%)
BR30 31,445 Increased By 1935.9 (6.56%)
KSE100 99,269 Increased By 4695.1 (4.96%)
KSE30 31,032 Increased By 1587.6 (5.39%)

Pakistan and Asian Development Bank (ADB) on Friday signed an agreement to invest 242 million dollars in improving power distribution system in the country. The signing ceremony was held here at Economic Affairs Division. The agreement was signed by Sibtain Fazal Halim, Secretary Economic Affairs Division and Rune Stroem, country director ADB, while the project agreement was signed by the representatives of all the 8 Distribution Companies (DISCOs).
The loan is meant for Tranche-2 of the Power Distribution Enhancement Investment Programme under Multi-tranche Financing Facility (MFF). ADB's total MFF programme is of 810 million dollars (US $800 million OCR and US $10 million ADF). The programme is comprised Multi-tranches and the same will be implemented in ten years period. The objective of the project is to rehabilitate, augment and expand power distribution systems and remove system bottlenecks in the project area.
The project shall add 3,380 Megavolt-Amperes (MVA) of transformer capacity, 387 km of new distribution lines, and improve security of supply to customers by moving toward compliance with regulatory security standards governing planning and operation of the distribution system and reliability improvement on the lower voltages. The project is expected to be completed by March 21. Speaking on the occasion the ADB's country director said that energy conservation and energy efficiency is the fastest and cheapest way of increasing electricity supply. "This project will not only reduce electricity lost during delivery to the customers but also improve the quality of service by helping to get rid of technical bottlenecks," he added.

Copyright Associated Press of Pakistan, 2011