AGL 37.99 Decreased By ▼ -0.03 (-0.08%)
AIRLINK 215.53 Increased By ▲ 18.17 (9.21%)
BOP 9.80 Increased By ▲ 0.26 (2.73%)
CNERGY 6.79 Increased By ▲ 0.88 (14.89%)
DCL 9.17 Increased By ▲ 0.35 (3.97%)
DFML 38.96 Increased By ▲ 3.22 (9.01%)
DGKC 100.25 Increased By ▲ 3.39 (3.5%)
FCCL 36.70 Increased By ▲ 1.45 (4.11%)
FFBL 88.94 No Change ▼ 0.00 (0%)
FFL 14.49 Increased By ▲ 1.32 (10.02%)
HUBC 134.13 Increased By ▲ 6.58 (5.16%)
HUMNL 13.63 Increased By ▲ 0.13 (0.96%)
KEL 5.69 Increased By ▲ 0.37 (6.95%)
KOSM 7.32 Increased By ▲ 0.32 (4.57%)
MLCF 45.87 Increased By ▲ 1.17 (2.62%)
NBP 61.28 Decreased By ▼ -0.14 (-0.23%)
OGDC 232.59 Increased By ▲ 17.92 (8.35%)
PAEL 40.73 Increased By ▲ 1.94 (5%)
PIBTL 8.58 Increased By ▲ 0.33 (4%)
PPL 203.34 Increased By ▲ 10.26 (5.31%)
PRL 40.81 Increased By ▲ 2.15 (5.56%)
PTC 28.31 Increased By ▲ 2.51 (9.73%)
SEARL 108.51 Increased By ▲ 4.91 (4.74%)
TELE 8.74 Increased By ▲ 0.44 (5.3%)
TOMCL 35.83 Increased By ▲ 0.83 (2.37%)
TPLP 13.84 Increased By ▲ 0.54 (4.06%)
TREET 24.38 Increased By ▲ 2.22 (10.02%)
TRG 61.15 Increased By ▲ 5.56 (10%)
UNITY 34.84 Increased By ▲ 1.87 (5.67%)
WTL 1.72 Increased By ▲ 0.12 (7.5%)
BR100 12,244 Increased By 517.6 (4.41%)
BR30 38,419 Increased By 2042.6 (5.62%)
KSE100 113,924 Increased By 4411.3 (4.03%)
KSE30 36,044 Increased By 1530.5 (4.43%)

LAHORE: Pakistan Water and Power Development Authority (WAPDA) Chairman Lt Gen Muzammil Hussain (Retd), has found serious technical issues relating to design, route and functionality of Greater Karachi Water Supply Scheme K-IV project, saying that the project could not be proceeded ahead without resolving these issues.

He has directed WAPDA team to compile a detailed report highlighting the major issues confronting the project and their possible solutions. Thereafter, a way forward will be determined to proceed further on the project, he added.

Chairman WAPDA, along with a high-level WAPDA technical team, visited (K-IV) Project the other day.

WAPDA technical team comprised of seasoned engineers of repute having vast experience in project implementation including Advisor (Projects), General Manager (Coordination & Monitoring) Water, General Manager (Central Design Office), General Manager (Hydro Planning) and General Manager (Projects) South.

In the first instance, WAPDA Chairman had a detailed round of the K-IV Intake located at Keenjhar Lake in District Thatta.

On the occasion, K-IV Project Director Government of Sindh made a briefing about the current status of the project, highlighting impediments in the way to construction of the scheme.

Frontier Works Organisation (FWO) Project Manager informed of the construction progress achieved so far on the project. While OCL Consultants Director made a detailed deliberation about the issues hampering the project.

Later, WAPDA Chairman and the project officers concerned also had an aerial view along with alignment of the project.

It is pertinent to mention that K-IV Project envisages to supply 260 million gallons per day of water to Karachi in Phase-I. The project was earlier being undertaken by the Sindh Government, however, the federal government, under an arrangement with the provincial government, has now taken up implementation of the project as part of the Prime Minister’s Package for Karachi and directed WAPDA to take over the implementation responsibilities of the project.