AGL 40.00 Decreased By ▼ -0.16 (-0.4%)
AIRLINK 129.53 Decreased By ▼ -2.20 (-1.67%)
BOP 6.68 Decreased By ▼ -0.01 (-0.15%)
CNERGY 4.63 Increased By ▲ 0.16 (3.58%)
DCL 8.94 Increased By ▲ 0.12 (1.36%)
DFML 41.69 Increased By ▲ 1.08 (2.66%)
DGKC 83.77 Decreased By ▼ -0.31 (-0.37%)
FCCL 32.77 Increased By ▲ 0.43 (1.33%)
FFBL 75.47 Increased By ▲ 6.86 (10%)
FFL 11.47 Increased By ▲ 0.12 (1.06%)
HUBC 110.55 Decreased By ▼ -1.21 (-1.08%)
HUMNL 14.56 Increased By ▲ 0.25 (1.75%)
KEL 5.39 Increased By ▲ 0.17 (3.26%)
KOSM 8.40 Decreased By ▼ -0.58 (-6.46%)
MLCF 39.79 Increased By ▲ 0.36 (0.91%)
NBP 60.29 No Change ▼ 0.00 (0%)
OGDC 199.66 Increased By ▲ 4.72 (2.42%)
PAEL 26.65 Decreased By ▼ -0.04 (-0.15%)
PIBTL 7.66 Increased By ▲ 0.18 (2.41%)
PPL 157.92 Increased By ▲ 2.15 (1.38%)
PRL 26.73 Increased By ▲ 0.05 (0.19%)
PTC 18.46 Increased By ▲ 0.16 (0.87%)
SEARL 82.44 Decreased By ▼ -0.58 (-0.7%)
TELE 8.31 Increased By ▲ 0.08 (0.97%)
TOMCL 34.51 Decreased By ▼ -0.04 (-0.12%)
TPLP 9.06 Increased By ▲ 0.25 (2.84%)
TREET 17.47 Increased By ▲ 0.77 (4.61%)
TRG 61.32 Decreased By ▼ -1.13 (-1.81%)
UNITY 27.43 Decreased By ▼ -0.01 (-0.04%)
WTL 1.38 Increased By ▲ 0.10 (7.81%)
BR100 10,407 Increased By 220 (2.16%)
BR30 31,713 Increased By 377.1 (1.2%)
KSE100 97,328 Increased By 1781.9 (1.86%)
KSE30 30,192 Increased By 614.4 (2.08%)

ISLAMABAD: The contractor could not be mobilised on Dera Ismail Khan-Zhob dual carriageway—major component of western route under the China-Pakistan Economic Corridor (CPEC) till the mobilization of Chinese Engineering, Procurement and Construction (EPC).

This was stated by the National Highways Authority (NHA) member West Zone Shahid Ihsanullah, while addressing an e-katchehri through the authority’ Facebook page.

The Dera Ismail Khan-Zhob section of N-50 was approved by the Executive Committee of the National Economic Council around over three years ago.

Despite a significant delay, major work on the project could not be started due to the unavailability of funds.

The dualisation of Quetta-Chaman-Karachi (N-250) road would be taken on Public Private Partnership (PPP) mode and the construction work on the project is expected to resume in the first quarter of 2021, the NHA official added.

He said that the government was in process of mobilizing consultant who would carry out financial viability of the project after which the project would be initiated in the first quarter of 2021.

A number of questions were raised during the e-katchehry while observing that accidents are common on this road and needs urgent attention of the government. Ihsanullah further said that only five toll are operational in Balochistan, while 13 are non-operational.

He said that the NHA collects around Rs36 billion which is totally allocated for maintenance.

He appealed to the public to pay toll tax for improving road condition.

He rejected the notion that roads condition in Balochistan is the main cause of accidents, while saying that speeding was the major cause of too many accidents.

Member NHA further said that NHA has a total network of 13,500 km across the country which carries around 80 percent of load capacity.

He further said that NHA has a network of around 3700 km in Balochistan.

Copyright Business Recorder, 2020