AGL 40.20 Decreased By ▼ -1.30 (-3.13%)
AIRLINK 129.11 Increased By ▲ 1.11 (0.87%)
BOP 6.60 Increased By ▲ 0.34 (5.43%)
CNERGY 4.03 Decreased By ▼ -0.10 (-2.42%)
DCL 8.45 Increased By ▲ 0.01 (0.12%)
DFML 41.25 Increased By ▲ 0.56 (1.38%)
DGKC 87.00 Decreased By ▼ -0.90 (-1.02%)
FCCL 33.35 Decreased By ▼ -0.75 (-2.2%)
FFBL 65.90 Decreased By ▼ -0.43 (-0.65%)
FFL 10.54 Decreased By ▼ -0.02 (-0.19%)
HUBC 110.70 Increased By ▲ 2.00 (1.84%)
HUMNL 15.23 Increased By ▲ 0.77 (5.33%)
KEL 4.78 Increased By ▲ 0.13 (2.8%)
KOSM 7.83 Increased By ▲ 0.50 (6.82%)
MLCF 41.90 Decreased By ▼ -0.82 (-1.92%)
NBP 60.50 Decreased By ▼ -0.34 (-0.56%)
OGDC 182.80 Increased By ▲ 3.83 (2.14%)
PAEL 25.36 Decreased By ▼ -0.34 (-1.32%)
PIBTL 6.26 Increased By ▲ 0.20 (3.3%)
PPL 147.81 Increased By ▲ 1.66 (1.14%)
PRL 24.56 Decreased By ▼ -0.35 (-1.41%)
PTC 16.24 Increased By ▲ 0.10 (0.62%)
SEARL 70.50 Increased By ▲ 0.30 (0.43%)
TELE 7.30 Increased By ▲ 0.08 (1.11%)
TOMCL 36.30 Increased By ▲ 0.10 (0.28%)
TPLP 7.85 Increased By ▲ 0.01 (0.13%)
TREET 15.30 Decreased By ▼ -0.29 (-1.86%)
TRG 51.70 Increased By ▲ 1.34 (2.66%)
UNITY 27.35 Increased By ▲ 0.45 (1.67%)
WTL 1.23 Decreased By ▼ -0.01 (-0.81%)
BR100 9,842 Increased By 47.4 (0.48%)
BR30 30,036 Increased By 389.6 (1.31%)
KSE100 92,520 Increased By 499.1 (0.54%)
KSE30 28,786 Increased By 121.7 (0.42%)

ISLAMABAD: The National Highways Authority (NHA)’s Executive Board has approved the annual maintenance plan (AMP) fiscal year (2020-21) amounting to Rs42.567 billion, in addition to carry forward liabilities from previous years amounting to Rs16.818 billion, along with carry forwarding un-awarded schemes of previous AMPs worth Rs3.684 billion.

The meeting of the NHA’s Executive Board was held with Capt (retd) Muhammad Khurram Agha, chairman NHA, in the chair.

The NHA Executive Board, unanimously, confirmed minutes of the previous meeting as per modifications suggested by the Board Members in the agenda item regarding, “Revision in Monetary Limits of Tender Opening, Evaluation & Acceptance Committee for Procurement of RMA Works”.

The NHA Executive Board deliberated upon and approved the AMP 2020-21 amounting to Rs42.567 billion, in addition to carry forward liabilities from previous years amounting to Rs16.818 billion, along with carry forwarding un-awarded schemes of previous AMPs worth Rs3.684 billion.

The board directed to present AMP 2021-22 before end of June 2022.

The board deliberated upon consultancy services for design review and construction supervision of Lodhran–Multan section (north bound 62km) of N-5 and two flyovers at railway crossing on Lodhran bypass.

The NHA Executive Board approved the award of agreement for Consultancy Services for “Design Review and Construction Supervision of Lodhran–Multan Section (North Bound 62 KM) of N-5 and two flyovers at Railway crossing on Lodhran bypass” to M/s Associated Consulting Engineers ACE Ltd in JV with M/s Associated Consultancy Centre (Pvt) Ltd and M/s ZAK Consulting Engineers (SMC-Pvt) Ltd, the highest-ranked consultants in the Combined (Technical + Financial) evaluation, at evaluated cost of Rs118.805 million including general sales tax (GST).

The NHA Executive Board approved revised contract cost as per addendum No 02 amounting to Rs133.970 million, which is 56.02 percent incremental to Addendum No 01 and 94.70 percent incremental to original contract cost.

The revised contract cost is comprising respective contractor’s share of Rs21.217 million (5.88 percent) and financial impact of NHA Rs112.386 million (84.12 percent).

The Addendum No 02 is based on actual consumption of supervision staff at site for Package-1A and Package-1B including (15-month) expected time and cost for Package-1C.

The overall length/duration of the consultancy services has been worked out (36.76+15) 51.76 months (from February 07, 2018 to February 28, 2021 i.e. 36.76 months and 15 months for construction of Package-1C from its re-commencement date).