AGL 40.00 Decreased By ▼ -0.16 (-0.4%)
AIRLINK 129.53 Decreased By ▼ -2.20 (-1.67%)
BOP 6.68 Decreased By ▼ -0.01 (-0.15%)
CNERGY 4.63 Increased By ▲ 0.16 (3.58%)
DCL 8.94 Increased By ▲ 0.12 (1.36%)
DFML 41.69 Increased By ▲ 1.08 (2.66%)
DGKC 83.77 Decreased By ▼ -0.31 (-0.37%)
FCCL 32.77 Increased By ▲ 0.43 (1.33%)
FFBL 75.47 Increased By ▲ 6.86 (10%)
FFL 11.47 Increased By ▲ 0.12 (1.06%)
HUBC 110.55 Decreased By ▼ -1.21 (-1.08%)
HUMNL 14.56 Increased By ▲ 0.25 (1.75%)
KEL 5.39 Increased By ▲ 0.17 (3.26%)
KOSM 8.40 Decreased By ▼ -0.58 (-6.46%)
MLCF 39.79 Increased By ▲ 0.36 (0.91%)
NBP 60.29 No Change ▼ 0.00 (0%)
OGDC 199.66 Increased By ▲ 4.72 (2.42%)
PAEL 26.65 Decreased By ▼ -0.04 (-0.15%)
PIBTL 7.66 Increased By ▲ 0.18 (2.41%)
PPL 157.92 Increased By ▲ 2.15 (1.38%)
PRL 26.73 Increased By ▲ 0.05 (0.19%)
PTC 18.46 Increased By ▲ 0.16 (0.87%)
SEARL 82.44 Decreased By ▼ -0.58 (-0.7%)
TELE 8.31 Increased By ▲ 0.08 (0.97%)
TOMCL 34.51 Decreased By ▼ -0.04 (-0.12%)
TPLP 9.06 Increased By ▲ 0.25 (2.84%)
TREET 17.47 Increased By ▲ 0.77 (4.61%)
TRG 61.32 Decreased By ▼ -1.13 (-1.81%)
UNITY 27.43 Decreased By ▼ -0.01 (-0.04%)
WTL 1.38 Increased By ▲ 0.10 (7.81%)
BR100 10,407 Increased By 220 (2.16%)
BR30 31,713 Increased By 377.1 (1.2%)
KSE100 97,328 Increased By 1781.9 (1.86%)
KSE30 30,192 Increased By 614.4 (2.08%)

ISLAMABAD: All Pakistan Textile Mills Association (APTMA) has accused power Distribution Companies (DISCOs) of not giving new connections or enhancing connections of existing units due to which production has reduced by up to 25 per cent.

The Association has made this claim in a letter to the newly-appointed Secretary Power, Rashid Mehmood Langrial. The Associations says that it works closely with the Ministry of Energy to ensure that its member mills have access to consistent and reliable energy. In this regard, APTMA has provided weekly updates to the Power Division regarding the issues in continuity of power supply to the industry and also those relating to non-conformity of laid-down standards.

The previously provided information from the previous six months noted that APTMA members units are continuously facing issues and that both interruptions and substandard supplies prevail resulting in the industry’s use of alternate fuels for production at a significant cost.

According to the letter, a closer look at the scenario indicates that the industry is frequently faced with wrongly timed maintenance shutdowns, emergency shutdowns, malfunctions, tripping, and bouts of supply dips and spikes.

“The unfortunate part is that despite direct engagement from the Power Division, APTMA has not been given confidence in the corrective measures implemented by any of the concerned DISCOs. “This circumstance brings us to the regrettable conclusion that, in all likelihood, the DISCOs were unable to do anything to ensure continuous and standard supply to the industry,” the Association continued.

APTMA further maintained that any interruption (even if it is shorter than one minute) or dip/ spike results in inflated disruption(s) in industrial activities, ranging from 10 to 20 minutes - all of which have a negative monetary worth of thousands of rupees for each mill.

The power companies are obliged to provide standard supply to the industry but no steps are taken to fix their problems, it said.

“At the same time, APTMA is not informed of any challenges that the DISCOs are experiencing, which could indicate that the situation is beyond the DISCOs’ capabilities or that the subject is not being given the attention that it deserves,” the Association maintained.

NEPRA previously allowed industrial consumers to increase their load capacity from 5 MW to 7.5 MW. It was interpreted by industry and later clarified by NEPRA (vide letter NEPRA/DG(CAD)/TCD-10/4012-24) that all such customers will be obliged to pay the proportionate cost of grid, including transmission line charges, as well as, the complete cost of land proportionate to the load. However, DISCOs misinterpreted NEPRA’s decision and charged industrial consumers in full. There are presently 108 load extension cases pending with DISCOs.

Despite NEPRA’S clarification, no demand notice has been revised. This prolonged delay caused by procedural issues is incomprehensible. Due to the lack of gas in the country many industrial units seek to switch to electricity; however, delays from DISCOS are reducing production capacity by 20 to 25 percent, resulting in significant loss to Pakistan’s exports/ economy.

APTMA requested Power Division to call a meeting with the DISCOs to map out a strategy for addressing its concerns including the delay in new and enhanced connections.