AGL 40.21 Increased By ▲ 0.18 (0.45%)
AIRLINK 127.64 Decreased By ▼ -0.06 (-0.05%)
BOP 6.67 Increased By ▲ 0.06 (0.91%)
CNERGY 4.45 Decreased By ▼ -0.15 (-3.26%)
DCL 8.73 Decreased By ▼ -0.06 (-0.68%)
DFML 41.16 Decreased By ▼ -0.42 (-1.01%)
DGKC 86.11 Increased By ▲ 0.32 (0.37%)
FCCL 32.56 Increased By ▲ 0.07 (0.22%)
FFBL 64.38 Increased By ▲ 0.35 (0.55%)
FFL 11.61 Increased By ▲ 1.06 (10.05%)
HUBC 112.46 Increased By ▲ 1.69 (1.53%)
HUMNL 14.81 Decreased By ▼ -0.26 (-1.73%)
KEL 5.04 Increased By ▲ 0.16 (3.28%)
KOSM 7.36 Decreased By ▼ -0.09 (-1.21%)
MLCF 40.33 Decreased By ▼ -0.19 (-0.47%)
NBP 61.08 Increased By ▲ 0.03 (0.05%)
OGDC 194.18 Decreased By ▼ -0.69 (-0.35%)
PAEL 26.91 Decreased By ▼ -0.60 (-2.18%)
PIBTL 7.28 Decreased By ▼ -0.53 (-6.79%)
PPL 152.68 Increased By ▲ 0.15 (0.1%)
PRL 26.22 Decreased By ▼ -0.36 (-1.35%)
PTC 16.14 Decreased By ▼ -0.12 (-0.74%)
SEARL 85.70 Increased By ▲ 1.56 (1.85%)
TELE 7.67 Decreased By ▼ -0.29 (-3.64%)
TOMCL 36.47 Decreased By ▼ -0.13 (-0.36%)
TPLP 8.79 Increased By ▲ 0.13 (1.5%)
TREET 16.84 Decreased By ▼ -0.82 (-4.64%)
TRG 62.74 Increased By ▲ 4.12 (7.03%)
UNITY 28.20 Increased By ▲ 1.34 (4.99%)
WTL 1.34 Decreased By ▼ -0.04 (-2.9%)
BR100 10,086 Increased By 85.5 (0.85%)
BR30 31,170 Increased By 168.1 (0.54%)
KSE100 94,764 Increased By 571.8 (0.61%)
KSE30 29,410 Increased By 209 (0.72%)

ISLAMABAD: Planning Commission (PC) has urged National Electric Power Regulatory Authority (Nepra) to allow cost-plus reflection of transportation cost of Thar coal in the tariff, to make utilization of indigenous coal viable. This was suggested by Planning Commission’s Member Energy during a meeting held on Thar coal convened on the directions of Prime Minister Shehbaz Sharif, who has constituted a committee to ascertain the availability and demand of Thar coal and commercial viability of Thar rail connectivity project.

Presided over by Minister for Planning, Development and Special Initiatives, Ahsan Iqbal, the meeting discussed pros and cons of availability and demand of Thar coal and commercial viability of Thar rail connectivity.

Minister for Planning, Development and Special Initiatives highlighted that as per Prime Minister’s directives the mandate of the committee is to ascertain the supply and demand of Thar coal in power and industrial sectors of the country and its transportation through railways, so that the funds allocation both by the federal and Sindh governments in the PSDP mode could be utilized prudently and effectively.

Member Energy, Planning Commission gave a presentation on the existing utilization of imported, as well as, domestic coal in power and non-power sectors of the country. He told the forum that presently three existing coal power plants, i.e., China Hub, China Power and Sahiwal are operating on imported coal while Lucky Electric and Jamshoro (with 20 per cent substitution) have confirmed utilization of 4.3 million ton of domestic coal.

300MW Gwadar plant: CPPCL unwilling to shift to Thar coal

Regarding utilization of Thar/ domestic coal by the above-mentioned three existing power plants, operated on imported coal, feasibility study is being conducted by PPIB. He further highlighted the safety issues of Thar coal transportation and storage and fluctuations in the international price of imported coal.

Member Energy apprised the committee that viability of Thar coal utilization depends on its transportation cost in the tariff of the power plant. Nepra should allow cost-plus reflection of transportation cost in the tariff.

On a query from the Chair regarding timeline for transportation of coal, Secretary Railways stated that Pakistan Railway would be able to transport coal by March, 2023. However, the complete scope of the PC-1 which included upgradation of stations, etc., would be completed in 17-month time.

SAPM on Effective Governance also emphasized that since the confirmed coal demand for Lucky Power Plant and Jamshoro (20 per cent substitution) is available; therefore, the agreement with both power plants should be finalized by the Power Division and provision of additional supply of Thar coal along with timeline would be confirmed by the Government of Sindh.

Copyright Business Recorder, 2022