AIRLINK 193.50 Increased By ▲ 1.66 (0.87%)
BOP 10.00 Increased By ▲ 0.13 (1.32%)
CNERGY 7.67 No Change ▼ 0.00 (0%)
FCCL 38.24 Increased By ▲ 0.38 (1%)
FFL 15.80 Increased By ▲ 0.04 (0.25%)
FLYNG 25.60 Increased By ▲ 0.29 (1.15%)
HUBC 130.60 Increased By ▲ 0.43 (0.33%)
HUMNL 13.82 Increased By ▲ 0.23 (1.69%)
KEL 4.68 Increased By ▲ 0.01 (0.21%)
KOSM 6.19 Decreased By ▼ -0.02 (-0.32%)
MLCF 44.82 Increased By ▲ 0.53 (1.2%)
OGDC 210.50 Increased By ▲ 3.63 (1.75%)
PACE 6.62 Increased By ▲ 0.06 (0.91%)
PAEL 40.95 Increased By ▲ 0.40 (0.99%)
PIAHCLA 17.80 Increased By ▲ 0.21 (1.19%)
PIBTL 8.12 Increased By ▲ 0.05 (0.62%)
POWER 9.11 Decreased By ▼ -0.13 (-1.41%)
PPL 182.35 Increased By ▲ 3.79 (2.12%)
PRL 39.51 Increased By ▲ 0.43 (1.1%)
PTC 24.36 Increased By ▲ 0.22 (0.91%)
SEARL 108.60 Increased By ▲ 0.75 (0.7%)
SILK 0.97 No Change ▼ 0.00 (0%)
SSGC 39.00 Decreased By ▼ -0.11 (-0.28%)
SYM 19.26 Increased By ▲ 0.14 (0.73%)
TELE 8.67 Increased By ▲ 0.07 (0.81%)
TPLP 12.40 Increased By ▲ 0.03 (0.24%)
TRG 65.80 Decreased By ▼ -0.21 (-0.32%)
WAVESAPP 12.60 Decreased By ▼ -0.18 (-1.41%)
WTL 1.70 No Change ▼ 0.00 (0%)
YOUW 3.95 No Change ▼ 0.00 (0%)
BR100 11,964 Increased By 33.3 (0.28%)
BR30 35,919 Increased By 259.6 (0.73%)
KSE100 113,970 Increased By 763.1 (0.67%)
KSE30 35,802 Increased By 236.4 (0.66%)

LAHORE: The Wapda has awarded contract Package XI of Mangla refurbishment project for units 9 and 10 to GE Hydro, France. The contract worth Rs11.922 billion includes manufacturing, supplying, installation and commissioning of the two units.

The contract signing ceremony was held at Wapda House on Tuesday. General Manager (Hydel) Development Wapda Ihsan Ullah and representative of GE Hydro France Abubakar signed the agreement on behalf of their organisations. Chairman Wapda Lt Gen Sajjad Ghani (retd), Member (Power) Wapda Jamil Akhtar, Project Director Mangla Refurbishment Project, senior officers, representatives of the consultants, and the contractors were also present on the occasion.

The Wapda is implementing Mangla Refurbishment Project with an approved PC-I cost of Rs 52.224 billion. The project is being carried out in various phases, wherein the generating units are to be refurbished by closing down one tunnel (two generating units) at a time.

The refurbishment works have been divided into 11 different packages. Prior to signing of Package-XI, nine other packages have already been awarded, while works on four packages have been completed. Refurbishment of the first two units has been completed in 2022, while refurbishment of all 10 generating units is likely to be accomplished by year 2026-27.

Mangla Refurbishment Project, on its completion, will enhance generation capacity of the existing Mangla Hydel Power Station from 1000 megawatt (MW) to 1310 MW, thus adding 310 MW additional power with average 1610 million units of additional energy per annum to the National Grid. It may be mentioned that the USAID is providing $ 150 million as grant and AFD is providing Euro 90 million as loan for Mangla Refurbishment Project, while rest of the amount is being arranged by WAPDA through loans and from its own resources.

Copyright Business Recorder, 2023