AGL 40.25 Increased By ▲ 0.09 (0.22%)
AIRLINK 130.28 Decreased By ▼ -1.45 (-1.1%)
BOP 6.70 Increased By ▲ 0.01 (0.15%)
CNERGY 4.57 Increased By ▲ 0.10 (2.24%)
DCL 9.01 Increased By ▲ 0.19 (2.15%)
DFML 41.26 Increased By ▲ 0.65 (1.6%)
DGKC 84.75 Increased By ▲ 0.67 (0.8%)
FCCL 32.64 Increased By ▲ 0.30 (0.93%)
FFBL 75.47 Increased By ▲ 6.86 (10%)
FFL 11.52 Increased By ▲ 0.17 (1.5%)
HUBC 110.50 Decreased By ▼ -1.26 (-1.13%)
HUMNL 14.31 No Change ▼ 0.00 (0%)
KEL 5.24 Increased By ▲ 0.02 (0.38%)
KOSM 8.82 Decreased By ▼ -0.16 (-1.78%)
MLCF 39.30 Decreased By ▼ -0.13 (-0.33%)
NBP 60.75 Increased By ▲ 0.46 (0.76%)
OGDC 195.40 Increased By ▲ 0.46 (0.24%)
PAEL 26.70 Increased By ▲ 0.01 (0.04%)
PIBTL 7.54 Increased By ▲ 0.06 (0.8%)
PPL 155.98 Increased By ▲ 0.21 (0.13%)
PRL 27.07 Increased By ▲ 0.39 (1.46%)
PTC 18.06 Decreased By ▼ -0.24 (-1.31%)
SEARL 81.90 Decreased By ▼ -1.12 (-1.35%)
TELE 8.35 Increased By ▲ 0.12 (1.46%)
TOMCL 34.57 Increased By ▲ 0.02 (0.06%)
TPLP 9.10 Increased By ▲ 0.29 (3.29%)
TREET 17.28 Increased By ▲ 0.58 (3.47%)
TRG 62.50 Increased By ▲ 0.05 (0.08%)
UNITY 27.60 Increased By ▲ 0.16 (0.58%)
WTL 1.36 Increased By ▲ 0.08 (6.25%)
BR100 10,388 Increased By 201 (1.97%)
BR30 31,493 Increased By 156.9 (0.5%)
KSE100 97,139 Increased By 1593 (1.67%)
KSE30 30,152 Increased By 573.7 (1.94%)

ISLAMABAD: The World Bank has rated the overall implementation progress of Pakistan Raises Revenue project of worth $400 million moderately satisfactory, observing that some key procurements are under way.

The Bank official documents revealed that $277.61 million, ie, 71 percent of the financing have been disbursed so far while undisbursed amount stands at $114.39 million.

The Bank stated that overall satisfactory progress is noted towards achievement of project development objectives and implementation of the results-based component of the project.

There is improved performance in several Disbursement Linked Indicators (DLIs). The withholding tax lines have been reduced from 58 in FY19 to 33 in FY22 (DLI 1).

World Bank approves $350mn financing for Pakistan

The detailed tax expenditure and evidence-based revenue forecast reports have been published in FY23, while a tax gap analysis report was published last year (DLI 2).

Under DLI 3, all four provinces have signed MOUs for data sharing with the Federal Board of Revenue (FBR), as well as MOUs for input adjustments in sales tax and have adopted FBR’s valuation tables for immoveable properties. FBR has added around 616 thousand new taxpayers, identified through automated data sharing, ICT based business Intelligence tools, survey and other enforcement methods.

Cumulatively, 1.079 million taxpayers were added during past four years (DLI 5). In FY23, the FBR completed 53 field audits of large taxpayers for cases selected by the risk-based selection tool and monitored by the Compliance Unit through Audit Management Information System (DLI 6).

On DLI 7 the single returns portal is planned to be piloted with the Punjab Revenue Authority (PRA) in 2023. The functionality of the system has been tested with telecom sector and PRA.

Customs processing has improved with the reduction in the frequency of physical inspections at the border – from a baseline of 60 percent goods declared through the red and yellow channels in FY19 to 33.42 percent in FY23 (DLI 8).

Simplification of FBR’s core business processes has surpassed its target. FBR has completed the review, redesign or simplification and automation of 5 additional business processes of tax administration in FY23 (cumulatively, 17 against the target of 15 business processes (DLI 9).

The FBR has continued to track the Key Performance Indicators and published the bi-annual results report for FY23 on its website. The annual report for FY23 is being finalized (DLI 10).

The implementation progress of component 2 is moderately satisfactory. Some key procurements are underway, including the preparation of site for data center and equipment for the Automated Entry Exit Systems (AEES) for airports; launching the procurement process for AEES equipment for airports; while the procurement process for the equipment for seaports will be launched soon.

Hiring of consultants is also under process for the Central Risk Management System and Post Clearance Audit through comprehensive Business Process Mapping and Reengineering of core business processes.

The specifications for other major procurements related with the upgradation of data centre or data warehouse, are being designed, which will inform the procurement process for the same.

Copyright Business Recorder, 2023

Comments

Comments are closed.

IMTIAZ CASSUM AGBOATWALA Dec 26, 2023 09:26am
Everyone talking of raising revenue. What about spending/utilization of the revenue collected , whether it is spent judiciously .
thumb_up Recommended (0)
Josphat Mwenda Dec 27, 2023 10:41am
Just one car I want I am in kenya how much
thumb_up Recommended (0)