AIRLINK 196.38 Increased By ▲ 4.54 (2.37%)
BOP 10.11 Increased By ▲ 0.24 (2.43%)
CNERGY 7.75 Increased By ▲ 0.08 (1.04%)
FCCL 38.10 Increased By ▲ 0.24 (0.63%)
FFL 15.74 Decreased By ▼ -0.02 (-0.13%)
FLYNG 24.54 Decreased By ▼ -0.77 (-3.04%)
HUBC 130.38 Increased By ▲ 0.21 (0.16%)
HUMNL 13.73 Increased By ▲ 0.14 (1.03%)
KEL 4.60 Decreased By ▼ -0.07 (-1.5%)
KOSM 6.19 Decreased By ▼ -0.02 (-0.32%)
MLCF 44.85 Increased By ▲ 0.56 (1.26%)
OGDC 206.51 Decreased By ▼ -0.36 (-0.17%)
PACE 6.58 Increased By ▲ 0.02 (0.3%)
PAEL 39.77 Decreased By ▼ -0.78 (-1.92%)
PIAHCLA 17.20 Decreased By ▼ -0.39 (-2.22%)
PIBTL 7.99 Decreased By ▼ -0.08 (-0.99%)
POWER 9.20 Decreased By ▼ -0.04 (-0.43%)
PPL 178.91 Increased By ▲ 0.35 (0.2%)
PRL 38.93 Decreased By ▼ -0.15 (-0.38%)
PTC 24.31 Increased By ▲ 0.17 (0.7%)
SEARL 109.27 Increased By ▲ 1.42 (1.32%)
SILK 1.00 Increased By ▲ 0.03 (3.09%)
SSGC 37.75 Decreased By ▼ -1.36 (-3.48%)
SYM 18.83 Decreased By ▼ -0.29 (-1.52%)
TELE 8.53 Decreased By ▼ -0.07 (-0.81%)
TPLP 12.14 Decreased By ▼ -0.23 (-1.86%)
TRG 64.76 Decreased By ▼ -1.25 (-1.89%)
WAVESAPP 12.11 Decreased By ▼ -0.67 (-5.24%)
WTL 1.64 Decreased By ▼ -0.06 (-3.53%)
YOUW 3.87 Decreased By ▼ -0.08 (-2.03%)
BR100 12,000 Increased By 69.2 (0.58%)
BR30 35,548 Decreased By -112 (-0.31%)
KSE100 114,256 Increased By 1049.3 (0.93%)
KSE30 35,870 Increased By 304.3 (0.86%)

LAHORE: Lahore Development Authority Director General Muhammad Ali Randhawa has directed the official concerned to expedite work on the second package of Controlled Access Corridor Closed Road Project and Ravi Bridge Expansion Project.

In this connection, he chaired a meeting on Monday to review the progress of ongoing mega projects. LDA Chief Engineer Israr Saeed, Chief Engineer Tepa Iqar Hussain, Director Engineering Mirza Inam, Director Headquarters Asif Hussain, NESPAK Project Coordinator Saqib Naeem and other related officers attended the meeting.

The LDA DG reviewed the daily target for early completion of Package One of the Controlled Access Corridor Closed Road Project and also discussed matters relating to all sections of Package Two.

While briefing the meeting about the Controlled Access Corridor Closed Road Project, Chief Engineer LDA Israr Saeed and Chief Engineer Tepa Iqar Hussain said that its first package between Niazi Chowk and Sigian was nearing completion and the work was in progress.

On the Ravi Bridge Expansion Project, the meeting was told that out of 96 girders needed for the expansion of Ravi Bridge, 40 have been prepared while the pile work was in progress round the clock and 33 piles have been completed.