AGL 38.00 Decreased By ▼ -0.25 (-0.65%)
AIRLINK 136.45 Decreased By ▼ -2.52 (-1.81%)
BOP 5.44 Decreased By ▼ -0.01 (-0.18%)
CNERGY 3.80 Increased By ▲ 0.01 (0.26%)
DCL 7.50 Decreased By ▼ -0.07 (-0.92%)
DFML 45.41 Decreased By ▼ -0.74 (-1.6%)
DGKC 78.52 Increased By ▲ 0.41 (0.52%)
FCCL 28.89 Decreased By ▼ -0.21 (-0.72%)
FFBL 57.00 Decreased By ▼ -0.10 (-0.18%)
FFL 9.27 Increased By ▲ 0.57 (6.55%)
HUBC 96.80 Decreased By ▼ -5.02 (-4.93%)
HUMNL 13.40 Decreased By ▼ -0.85 (-5.96%)
KEL 3.77 Decreased By ▼ -0.05 (-1.31%)
KOSM 7.28 Decreased By ▼ -0.12 (-1.62%)
MLCF 37.80 Decreased By ▼ -0.55 (-1.43%)
NBP 67.50 Decreased By ▼ -2.00 (-2.88%)
OGDC 167.52 Decreased By ▼ -2.50 (-1.47%)
PAEL 25.10 Decreased By ▼ -0.55 (-2.14%)
PIBTL 6.70 Increased By ▲ 0.10 (1.52%)
PPL 131.50 Decreased By ▼ -2.08 (-1.56%)
PRL 26.40 Increased By ▲ 1.40 (5.6%)
PTC 15.10 Decreased By ▼ -0.44 (-2.83%)
SEARL 62.25 Decreased By ▼ -1.58 (-2.48%)
TELE 7.00 Increased By ▲ 0.05 (0.72%)
TOMCL 36.23 Decreased By ▼ -0.75 (-2.03%)
TPLP 7.88 Increased By ▲ 0.18 (2.34%)
TREET 14.00 Increased By ▲ 0.04 (0.29%)
TRG 44.55 Decreased By ▼ -0.42 (-0.93%)
UNITY 25.85 Increased By ▲ 0.45 (1.77%)
WTL 1.22 No Change ▼ 0.00 (0%)
BR100 9,143 Decreased By -61.6 (-0.67%)
BR30 27,326 Decreased By -391.2 (-1.41%)
KSE100 85,585 Decreased By -620.2 (-0.72%)
KSE30 26,984 Decreased By -252.2 (-0.93%)

ISLAMABAD: The National Highway Authority (NHA) Executive Board recommended the PC-I for the approval of Central Development Working Party (CDWP)/ Executive Committee of National Economic Council (ECNEC) for construction of Kharian- Rawalpindi Motorway at the revised PC-I cost of Rs 169.323 billion against the initial PC-1 cost of Rs 108.41 billion i.e. increased by around 57 percent.

Official documents further revealed that the revised PC-I cost of Rs 169.323 billion including capital Viability Gap Funding (VGF) of Rs 40 billion (Capital VGF 20 billion + Sub-debt VGF 20 billion) and operational VGF of PKR Nil up to KIBOR 10 percent whereas financial subsidy will be borne by the government, if KIBOR remains more than 10 percent during debt servicing period.

The meeting was presided over by Arshad Majeed Mohmand, Chairman, NHA which allowed submission of project qualification proposal (PQP) on similar lines to Public Private Partnership Authority (P3A) for soliciting their approval as per P3A Act.

Kharian-Rawalpindi Motorway: Project to be executed on BOT basis under PPP mode

ECNEC had earlier approved Kharian-Rawalpindi Motorway project in January 2022 with a total cost of the project was Rs 108.41 billion including government share of Rs 36.112 billion [Capital - Viability Gap Funding (VGF): Rs 7.5 billion, overhead costs: Rs 16.012 billion, operational VGF): Rs 12.6 billion] and Concessionaire share is Rs 72.298 billion.

Official sources revealed that a total of three bidders were in the run to get the project. However, a consortium M/s Techno-Matracon (JV) in association with M/s Powerchina Chengdu as Lead Constructor and M/s ACC as Design & Supervision Consultant was declared as successful bidder and a letter of intent (LOI) was issued to build Kharian-Rawalpindi Motorway project. The Techno-Matracon JC and Power China Chengdu Engineering Corporation Limited were required to obtain confirmation from Power China Chengdu about its lead role and percentage share to substantiate the submission of the bidder. The bidder failed to address the key observations of the revocable LOI and therefore, the NHA executive board withdrew the LOI and annulment of the procurement process.

The Board directed that, in future, the bidder be granted 15 days extendable for another period of 15 days for clarification of observation in LOI to avoid the inordinate delay for execution of project.

The project was supposed to be completed in two years and the total length of the motorway was 117.2 kilometers with 4-lane access-controlled from Kharian to Rawalpindi. This new motorway facility will be an extension of the currently operational Lahore-Sialkot Motorway and under construction Sialkot-Kharian Motorway. The project initiates from the junction interchange near Kharian on Sialkot-Kharian Motorway and terminates at T-Chowk near Rawalpindi/Islamabad.

The proposed motorway traverses parallel to the N-5, passing the populous areas of Jhelum, Mangla, Dina, Sohawa, Gujar Khan, Mandra, and finally terminating near Rawat at T-Chowk (Junction of Islamabad Expressway with N-5).

Copyright Business Recorder, 2024

Comments

Comments are closed.

ahmad faraz Feb 26, 2024 02:37pm
Poor bidding process with lacunas favoring the bidders costed 61 billion more or 56% jump in Project cost and who are the bigwigs responsible for it.
thumb_up Recommended (0)
Parvez Iqbal Malik Feb 26, 2024 06:56pm
This is beyond belief that we can spare over a 100 billion for a motorway for cities already connected by GT Road when thousands of communities in rural areas are suffering due to dirt roads or none.