AGL 40.21 Increased By ▲ 0.18 (0.45%)
AIRLINK 127.64 Decreased By ▼ -0.06 (-0.05%)
BOP 6.67 Increased By ▲ 0.06 (0.91%)
CNERGY 4.45 Decreased By ▼ -0.15 (-3.26%)
DCL 8.73 Decreased By ▼ -0.06 (-0.68%)
DFML 41.16 Decreased By ▼ -0.42 (-1.01%)
DGKC 86.11 Increased By ▲ 0.32 (0.37%)
FCCL 32.56 Increased By ▲ 0.07 (0.22%)
FFBL 64.38 Increased By ▲ 0.35 (0.55%)
FFL 11.61 Increased By ▲ 1.06 (10.05%)
HUBC 112.46 Increased By ▲ 1.69 (1.53%)
HUMNL 14.81 Decreased By ▼ -0.26 (-1.73%)
KEL 5.04 Increased By ▲ 0.16 (3.28%)
KOSM 7.36 Decreased By ▼ -0.09 (-1.21%)
MLCF 40.33 Decreased By ▼ -0.19 (-0.47%)
NBP 61.08 Increased By ▲ 0.03 (0.05%)
OGDC 194.18 Decreased By ▼ -0.69 (-0.35%)
PAEL 26.91 Decreased By ▼ -0.60 (-2.18%)
PIBTL 7.28 Decreased By ▼ -0.53 (-6.79%)
PPL 152.68 Increased By ▲ 0.15 (0.1%)
PRL 26.22 Decreased By ▼ -0.36 (-1.35%)
PTC 16.14 Decreased By ▼ -0.12 (-0.74%)
SEARL 85.70 Increased By ▲ 1.56 (1.85%)
TELE 7.67 Decreased By ▼ -0.29 (-3.64%)
TOMCL 36.47 Decreased By ▼ -0.13 (-0.36%)
TPLP 8.79 Increased By ▲ 0.13 (1.5%)
TREET 16.84 Decreased By ▼ -0.82 (-4.64%)
TRG 62.74 Increased By ▲ 4.12 (7.03%)
UNITY 28.20 Increased By ▲ 1.34 (4.99%)
WTL 1.34 Decreased By ▼ -0.04 (-2.9%)
BR100 10,086 Increased By 85.5 (0.85%)
BR30 31,170 Increased By 168.1 (0.54%)
KSE100 94,764 Increased By 571.8 (0.61%)
KSE30 29,410 Increased By 209 (0.72%)
Print Print 2024-03-19

Coal shortage period: Chinese may be allowed to declare OFME

  • This understanding will be part of minutes of next Energy Planning Expert Panel (EPEP) of China Pakistan Economic Corridor
Published March 19, 2024

ISLAMABAD: The government is likely to allow Chinese coal power plants to declare coal shortage period as Other Force Majeure Event (OFME) in line with settlement done in the past with other IPPs facing fuel shortages, well-informed sources in PPIB told Business Recorder.

This understanding, sources said, will be part of minutes of next Energy Planning Expert Panel (EPEP) of China Pakistan Economic Corridor (CPEC) to review progress and ensure smooth and timely implementation of energy projects initiated under CPEC.

Both sides will observe that 17 power generation projects of 8020 MW based on imported coal, Thar coal, wind, solar and hydropower had been commissioned besides a flag-ship HVDC transmission line project (1000 MW) accruing investment of about $ 18.94 billion (including the coal mine). One project, Suki Kinari 884 MW hydropower project, of $ 1.707 billion was under construction.

Coal power project at Gwadar: Chinese firm shows ‘conditional’ willingness to commence work

Three generation projects of 2124.7 MW (Gwadar, Kohala, Azad Pattan) based on coal and hydropower with an investment of about $ 4.157 billion are at an advance stage to achieve financial closing, whereas, four generation projects of 2020 MW (Oracle TharVI-1320 MW, Cacho Wind-50 MW, Western Wind-50 MW, Quaid-e-Azam Solar-600 MW) are at LoI stage.

Pakistan side gave briefing on opening of Revolving Account, as required under the provisions of Article-V of CPEC Agreement. It was apprised that to improve payments to CPEC IPPs, Government of Pakistan has opened and operationalised the Pakistan Energy Revolving Account (PERA) with State Bank of Pakistan (SBP) for all commissioned IPPs. The PERA has been adequately funded by Government of Pakistan.

Recently, China side put queries about: (i) how does Ministry of Finance provide security? (ii) what are the specific operational procedures in the case of PERA; (iii) regarding PERA, how to deal with the revision with the CPEC agreement? And (iv) what are the opinions of lender banks upon such amendments?

According to sources, Pakistan explained that: (i) Ministry of Finance will create budget allocation every year for payment to CPEC IPPs in addition to what CPPA-G is paying from its collection from Distribution Companies; (ii) without any demand from Banks or calling upon any Letter of Credit (LC), CPEC IPPs get funds directly to their accounts on monthly basis, through direct credit from State Bank of Pakistan; (iii) the procedure is better as through this procedure additional cash flow is generated for the CPEC IPPs. If lending banks accept this procedure, Pakistan side is ready to make required amendments in the Agreements; and (iv) China side should facilitate in getting recognition of PERA by lenders. Pakistan side further stated that opening of PERA will take care of the expected monthly shortfall which presently is much less than 22%. Therefore, the requirement for opening of Revolving Account is considered to be satisfied.

China side highly appreciated Pakistani side efforts in improving the tariff payments, however, current foreign exchange situation has led to severe difficulties regarding coal procurement. China side noted that in case power projects are unable to procure coal due to foreign exchange non-availability issues, no capacity payment be deducted for these projects by CPPA-G. Pakistan side appreciated the concern of CPEC IPPs and as an amicable solution, proposed that these IPPs may declare such period as Other Force Majeure Event (OFME) in line with settlement done in the past with other IPPs having fuel shortage issues. This option will require contractual modifications and approvals from appropriate forum for treatment of such event as OFME. China side appreciated the proposal and ensured to resolve the issue in consultation with CPEC IPPs.

Copyright Business Recorder, 2024

Comments

Comments are closed.

Tofique qureshi Mar 19, 2024 07:06am
What is the current status of usage of local thar coal in coal fire Chinese plants operated in Pak. When will the Huge reserves of thar coal be used. Do we still need imported coal?
thumb_up Recommended (0)
Cool boy Mar 19, 2024 08:25am
What does it means? Pakistan will continue to pay?
thumb_up Recommended (0)
Mudasir Mar 19, 2024 09:17am
I need help plz
thumb_up Recommended (0)
KU Mar 19, 2024 12:25pm
One remembers policy papers on availability of cheap coal in Pakistan a few years ago, and backed by usual feel-good articles in its support, so what happened? Incompetence or dishonesty at play?
thumb_up Recommended (0)
Kaleem Mar 19, 2024 11:52pm
With due respects, my sentiments are as under: در فٹے منہ
thumb_up Recommended (0)
Haris Mar 20, 2024 08:31am
@KU, what else sir?
thumb_up Recommended (0)