AGL 38.02 Increased By ▲ 0.08 (0.21%)
AIRLINK 197.36 Increased By ▲ 3.45 (1.78%)
BOP 9.54 Increased By ▲ 0.22 (2.36%)
CNERGY 5.91 Increased By ▲ 0.07 (1.2%)
DCL 8.82 Increased By ▲ 0.14 (1.61%)
DFML 35.74 Decreased By ▼ -0.72 (-1.97%)
DGKC 96.86 Increased By ▲ 4.32 (4.67%)
FCCL 35.25 Increased By ▲ 1.28 (3.77%)
FFBL 88.94 Increased By ▲ 6.64 (8.07%)
FFL 13.17 Increased By ▲ 0.42 (3.29%)
HUBC 127.55 Increased By ▲ 6.94 (5.75%)
HUMNL 13.50 Decreased By ▼ -0.10 (-0.74%)
KEL 5.32 Increased By ▲ 0.10 (1.92%)
KOSM 7.00 Increased By ▲ 0.48 (7.36%)
MLCF 44.70 Increased By ▲ 2.59 (6.15%)
NBP 61.42 Increased By ▲ 1.61 (2.69%)
OGDC 214.67 Increased By ▲ 3.50 (1.66%)
PAEL 38.79 Increased By ▲ 1.21 (3.22%)
PIBTL 8.25 Increased By ▲ 0.18 (2.23%)
PPL 193.08 Increased By ▲ 2.76 (1.45%)
PRL 38.66 Increased By ▲ 0.49 (1.28%)
PTC 25.80 Increased By ▲ 2.35 (10.02%)
SEARL 103.60 Increased By ▲ 5.66 (5.78%)
TELE 8.30 Increased By ▲ 0.08 (0.97%)
TOMCL 35.00 Decreased By ▼ -0.03 (-0.09%)
TPLP 13.30 Decreased By ▼ -0.25 (-1.85%)
TREET 22.16 Decreased By ▼ -0.57 (-2.51%)
TRG 55.59 Increased By ▲ 2.72 (5.14%)
UNITY 32.97 Increased By ▲ 0.01 (0.03%)
WTL 1.60 Increased By ▲ 0.08 (5.26%)
BR100 11,727 Increased By 342.7 (3.01%)
BR30 36,377 Increased By 1165.1 (3.31%)
KSE100 109,513 Increased By 3238.2 (3.05%)
KSE30 34,513 Increased By 1160.1 (3.48%)

ISLAMABAD: National Engineering Services Pakistan (Pvt) Limited is jubilant over hi-pot testing of transmission line of 884 MW Suki Kinari hydropower project within the timeframe.

In a letter to National Transmission and Despatch Company (NTDC), NESKPAK has conveyed felicitation on successful Hi-Pot Testing of the subject 500kV Transmission Line from Suki Kinari Hydro Power Plant to the Interconnection Point of existing 500kV Neelum Jhelum 500kV Transmission Line on June 27, 2024, which is termed an achievement of a massive milestone for all stakeholders, working tirelessly to harness and transmit cheaper electricity to the public of Pakistan.

NESPAK acknowledged that the design and engineering techniques involved in successful construction of the Transmission Line on the toughest terrain, faced by NTDC so far, embracing sheer difficulties in the face of pandemic driven problems as well as local weather and hilly area specific problems, is not less than an Engineering Marvel.

Suki Kinari Hydropower Station: First Unit registers success

“This achievement of executing, so far, the toughest 500kV Double Circuit Transmission Line Project by NTDC would certainly not have been possible today without the sheer dedication and tireless efforts of all stakeholders,” said Nadeem Ashraf, Executive Vice President/head Power and Mechanical Division, NESPAK. He has also commended the dedicated role and unwavering commitment of General Manager (Project Delivery North) NTDC Arif Khan, Chief Engineer (EHV-I) North NTDC Asghar Mujtaba Khan Niazi and entire NTDC team, under whose able leadership coupled with NESPAK management’s vision, experience, engineering acumen and round the clock efforts of the entire team of NESPAK, this engineering marvel was actually successfully realized. “I must also appreciate the dedication and commitment of the Contractor M/s CEEC NEPC-II, the Contractor’s representatives M.K Engineers & Constructors and all the engaged Subcontractors with whose relentless efforts we have been able to surmount this uphill task,” he added.

According to Power Division, overcoming logistical hurdles and ensuring local accessibility have been pivotal. Approaches to the towers have been wisely planned for not only the transportation of substantial materials to the inaccessible locations but also to ease local commuting. The contractor’s exceptional methodology for safely executing the project has set a new benchmark for similar projects. By opting not to construct the bridge and cable cars, despite their inclusion and perceived necessity in the contract, the contractor has significantly saved time and resources. This approach will be beneficial and helpful for future Projects.

The project was first envisaged in 1960, and feasibility studies have been carried out by German GTZ, Quebec based Montreal Engineering and recent detailed design and engineering study was performed by Mott MacDonald of England.

Copyright Business Recorder, 2024

Comments

Comments are closed.

Az_Iz Jul 05, 2024 05:12am
Great. Congratulations to everyone who was involved.
thumb_up Recommended (0)
M. Zahid Iftikhar Jul 05, 2024 12:19pm
Great achievement. I wish transmission lines for Patrind project could also have been installed at similar speed.
thumb_up Recommended (0)
Kureshi Jul 05, 2024 12:48pm
Great work. We hope that Neelum jhelum like situation will never happen here bcz here too we have long underground race tunnel
thumb_up Recommended (0)
Zubair Edhy Jul 05, 2024 08:14pm
"The project was first envisaged in 1960". And now it is 2024. Just 64 years.
thumb_up Recommended (0)