AIRLINK 170.57 Decreased By ▼ -2.58 (-1.49%)
BOP 11.18 Increased By ▲ 0.53 (4.98%)
CNERGY 8.41 Decreased By ▼ -0.11 (-1.29%)
CPHL 99.73 Increased By ▲ 2.27 (2.33%)
FCCL 46.60 Decreased By ▼ -0.65 (-1.38%)
FFL 15.15 Decreased By ▼ -0.27 (-1.75%)
FLYNG 27.55 Decreased By ▼ -0.58 (-2.06%)
HUBC 137.78 Decreased By ▼ -1.13 (-0.81%)
HUMNL 12.92 Increased By ▲ 0.11 (0.86%)
KEL 4.54 No Change ▼ 0.00 (0%)
KOSM 5.36 Decreased By ▼ -0.19 (-3.42%)
MLCF 62.40 Increased By ▲ 0.14 (0.22%)
OGDC 212.16 Decreased By ▼ -2.59 (-1.21%)
PACE 5.42 Decreased By ▼ -0.13 (-2.34%)
PAEL 47.18 Increased By ▲ 2.32 (5.17%)
PIAHCLA 18.48 Decreased By ▼ -0.22 (-1.18%)
PIBTL 10.36 Decreased By ▼ -0.38 (-3.54%)
POWER 12.33 Increased By ▲ 0.07 (0.57%)
PPL 169.60 Decreased By ▼ -4.27 (-2.46%)
PRL 35.85 Decreased By ▼ -0.37 (-1.02%)
PTC 23.09 Decreased By ▼ -0.47 (-1.99%)
SEARL 96.26 Increased By ▲ 0.95 (1%)
SSGC 39.52 Increased By ▲ 0.39 (1%)
SYM 13.84 Decreased By ▼ -0.18 (-1.28%)
TELE 7.15 Decreased By ▼ -0.08 (-1.11%)
TPLP 10.03 Decreased By ▼ -0.26 (-2.53%)
TRG 63.48 Decreased By ▼ -1.20 (-1.86%)
WAVESAPP 9.99 Decreased By ▼ -0.05 (-0.5%)
WTL 1.31 Decreased By ▼ -0.02 (-1.5%)
YOUW 3.66 Decreased By ▼ -0.04 (-1.08%)
BR100 12,305 Decreased By -186.6 (-1.49%)
BR30 37,415 Decreased By -278.7 (-0.74%)
KSE100 114,853 Decreased By -1335.9 (-1.15%)
KSE30 35,217 Decreased By -533.1 (-1.49%)

LAHORE: Chairman Wapda Engr Lt Gen Sajjad Ghani (r) visited under-construction 1530 MW-Tarbela 5th Extension and reviewed the progress on the project.

The Chairman had a detailed visit of the key sites, which include the raised intake, the tunnel and the power house, and witnessed the construction work. During the on-site briefing, the Project Director and the Construction Manager briefed the Chairman about the milestone achieved on these sites.

Temporary support work in the tunnel is complete paving the way for commencement of construction on the connecting tunnel. Installation of equipment such as draft tubes of all three units - Unit No 18, 19 and 20 - is in progress at the power house site. While, the Contractor is all set to resume construction work on the raised intake structure once the water in the reservoir recedes to the required level.

Following the site visit, the Chairman presided over a meeting at the project office attended by the GM Tarbela Dam, PD T5, the Consultants and the Contractors. Overall progress on the project was discussed during the meeting.

It was briefed that construction is continuing on all six work fronts simultaneously. The project is likely to be completed in 2025-26. Thorough deliberations were also made on the work plan for meeting the timelines. The Chairman was of the view that concerted efforts are needed on part of the Consultants and the Contractor to complete the project as per the schedule. Deployment of additional resources is also inevitable for the purpose, he said.

Tarbela 5th Extension Hydropower Project is a component of green, clean and least-cost energy generation plan of Wapda. World Bank and Asian Infrastructure Investment Bank are providing financial assistance for the project to the tune of $390 million and $300 million respectively.