AGL 40.00 Decreased By ▼ -0.01 (-0.02%)
AIRLINK 127.00 Decreased By ▼ -0.99 (-0.77%)
BOP 6.68 Increased By ▲ 0.08 (1.21%)
CNERGY 4.49 Decreased By ▼ -0.11 (-2.39%)
DCL 8.60 Increased By ▲ 0.12 (1.42%)
DFML 41.30 Decreased By ▼ -0.18 (-0.43%)
DGKC 86.71 Increased By ▲ 0.13 (0.15%)
FCCL 32.16 Increased By ▲ 0.02 (0.06%)
FFBL 64.70 Decreased By ▼ -0.72 (-1.1%)
FFL 10.29 Increased By ▲ 0.04 (0.39%)
HUBC 109.51 Decreased By ▼ -0.98 (-0.89%)
HUMNL 14.90 Increased By ▲ 0.15 (1.02%)
KEL 5.05 Decreased By ▼ -0.08 (-1.56%)
KOSM 7.40 Increased By ▲ 0.28 (3.93%)
MLCF 41.39 Decreased By ▼ -0.26 (-0.62%)
NBP 60.60 Increased By ▲ 0.51 (0.85%)
OGDC 190.00 Decreased By ▼ -4.69 (-2.41%)
PAEL 27.81 Decreased By ▼ -0.14 (-0.5%)
PIBTL 7.75 Decreased By ▼ -0.25 (-3.13%)
PPL 149.75 Decreased By ▼ -1.42 (-0.94%)
PRL 26.73 Decreased By ▼ -0.15 (-0.56%)
PTC 16.18 Increased By ▲ 0.18 (1.13%)
SEARL 86.02 Increased By ▲ 7.82 (10%)
TELE 7.72 Increased By ▲ 0.33 (4.47%)
TOMCL 35.58 Decreased By ▼ -0.09 (-0.25%)
TPLP 8.14 Increased By ▲ 0.23 (2.91%)
TREET 16.51 Increased By ▲ 0.62 (3.9%)
TRG 53.35 Increased By ▲ 0.59 (1.12%)
UNITY 26.28 Decreased By ▼ -0.27 (-1.02%)
WTL 1.26 Decreased By ▼ -0.01 (-0.79%)
BR100 9,889 Decreased By -31.1 (-0.31%)
BR30 30,611 Decreased By -140.9 (-0.46%)
KSE100 93,355 Increased By 130.9 (0.14%)
KSE30 28,931 Increased By 46 (0.16%)

ISLAMABAD: Power Division is all set to place a summary before the Economic Coordination Committee (ECC) of the Cabinet for approval of security package documents of 7.08 MW Riali-II Hydropower project under Power Generation Policy, 2015, sources told Business Recorder.

However, Finance Division is of the view that Power Division may ensure that proposed documents are consistent with the Power Generation Policy 2015 in respect of contractual matters i.e. no further obligations and guarantees are created over and above what have been offered under the policy.

According to Finance Division, GoP will not be assumed any obligation for payment of Water Use Charges (WUC) to the AJ&K, with the stance that same to be paid by the IPPs from its tariff.

Hydropower project: Riali-II to be processed on ‘must run & take-and-pay’ basis

Recently, PPIB Board had accorded approval for extension in the Financial Closing Date under the Tripartite Letter of Support (TLOS) of 7.08 MW Riali Hydropower Project for a period 18 months i.e. from April 13, 2024 to October 12, 2025.

During the meeting MD PPIB apprised that 7.08 MW Riali-II Hydropower Project is run of river project located on Ghori Nullah, in AJK.

Due to the no availability of ECC approved Security Documents (Implementation Agreement GoPIA - AJ&K Implementation Agreement-AJ&KlA, Energy Purchase Agreement-EPA and Water Use Agreement - WUA) for small hydro power projects, three extensions of 12 months each on Sept 7,2021, December 29, 2022 and November 10, 2023, respectively, were granted in the Tripartite Letter of Support.

As per the Amendment#3 (3rd Extension) of TLOS, the Project Company was required to sign the Project Agreements before Financial Close of the project for which they approached SIFC for early processing of approval of Project Agreements from CCoE/ECC.

Accordingly, summary was considered by the CCOE on July5, 2024 and it concurred with the proposal. Now, the standard documents are under process for ECC approval through Ministry of Energy (Power Division).

As per the commitment of the Project Company and present progress status of project, the Project Company will require 14 to 18 months to achieve its Commercial Operation after being provided with drafts of approved Security Agreements.

The Project Company has already started civil construction work of the Project from its equity and 60-65% of overall work has been completed at the Project site.

The Board was apprised that the Project Company has requested exemption from the payment of TLoS extension fee stating the reason that the delays in the provision of project agreements were not in the Company’s purview. Although there is no such provision in PPIB Fee and Charges Amendment Rules 2022 which allow waiver of fee to this project.

MD PPIB further explained that the matter was submitted for perusal of Projects’ Committee of PPIB Board in its ’11ih meeting, which recommended an extension of 18 months on single performance guarantee.

The Board approved extension in the Financial Closing date under the Tripartite Letter of Support of 7.08 MW Riali Hydropower Project for a period of 18 months, ie, from April 13, 2024 to October 12, 2025 subject to the followings:

(i) extension will be granted on the basis of a Single Performance Guarantee, in line with Clause 8.4

(ii) (c) of the Power Policy 2015, as the reasons for delay in the achievement of Financial Closing were beyond the reasonable control of the Project Company; and

(iii) the Project Company shall extend the validity of the Bank Guarantee three months beyond the allowed period of extension, and applicable extension fee shall be paid in accordance with PPIB Fee and Charges Amendment Rules 2022.

Copyright Business Recorder, 2024