AIRLINK 193.77 Decreased By ▼ -6.98 (-3.48%)
BOP 9.87 Decreased By ▼ -0.34 (-3.33%)
CNERGY 7.57 Decreased By ▼ -0.14 (-1.82%)
FCCL 39.41 Decreased By ▼ -0.65 (-1.62%)
FFL 16.29 Decreased By ▼ -0.52 (-3.09%)
FLYNG 25.84 Decreased By ▼ -0.81 (-3.04%)
HUBC 129.86 Decreased By ▼ -2.74 (-2.07%)
HUMNL 13.83 Decreased By ▼ -0.09 (-0.65%)
KEL 4.53 Decreased By ▼ -0.12 (-2.58%)
KOSM 6.47 Decreased By ▼ -0.12 (-1.82%)
MLCF 45.57 Decreased By ▼ -1.17 (-2.5%)
OGDC 209.11 Decreased By ▼ -3.32 (-1.56%)
PACE 6.72 Decreased By ▼ -0.18 (-2.61%)
PAEL 41.85 Increased By ▲ 0.57 (1.38%)
PIAHCLA 17.13 Increased By ▲ 0.13 (0.76%)
PIBTL 7.90 Decreased By ▼ -0.21 (-2.59%)
POWER 9.36 Decreased By ▼ -0.06 (-0.64%)
PPL 177.92 Decreased By ▼ -3.54 (-1.95%)
PRL 39.01 Decreased By ▼ -2.77 (-6.63%)
PTC 25.53 Increased By ▲ 0.83 (3.36%)
SEARL 106.73 Decreased By ▼ -5.11 (-4.57%)
SILK 0.99 Decreased By ▼ -0.01 (-1%)
SSGC 39.53 Decreased By ▼ -4.39 (-10%)
SYM 19.45 Increased By ▲ 0.47 (2.48%)
TELE 8.64 Decreased By ▼ -0.23 (-2.59%)
TPLP 12.53 Decreased By ▼ -0.39 (-3.02%)
TRG 65.34 Decreased By ▼ -2.13 (-3.16%)
WAVESAPP 11.15 Decreased By ▼ -0.27 (-2.36%)
WTL 1.73 Decreased By ▼ -0.06 (-3.35%)
YOUW 3.94 Decreased By ▼ -0.05 (-1.25%)
BR100 12,030 Decreased By -140.3 (-1.15%)
BR30 35,812 Decreased By -776.7 (-2.12%)
KSE100 113,520 Decreased By -1360.2 (-1.18%)
KSE30 35,651 Decreased By -473.7 (-1.31%)
Print Print 2024-12-26

2,160MW Dasu project: Ministry told to speed up revised PC-1 process

  • Ministry of Economic Affairs asks Ministry of Water Resources to ensue availability of the Additional Financing for implementation of the project activities
Published December 26, 2024

ISLAMABAD: The Ministry of Economic Affairs has asked the Ministry of Water Resources to expedite the submission and approval of revised PC-1 of 2,160 MW Dasu hydropower stage-1 project from the government’s competent fora in order to ensure signing and effectiveness of the negotiated loan and financing agreements well before the existing closing date, sources in the EAD told Business Recorder.

The MoEA in a letter to MoWR has informed that during negotiations for the second additional financing for the Dasu Hydropower Stage-1 project held with the World Bank on April 29, 2024 in which it was principally agreed to extend the closing date of the project (including for the subject IBRD loan for the Dasu Transmission Line) up to December 3l, 2028.

However, due to the pending approval of revised PC-1 for the Dasu Hydropower stage-1 project, the negotiated loan and financing agreements of the additional financing having incorporated the extended closing date for the project remain unsigned.

MoEA concerned about slow work at DHP

The MoEA is of the view that the fast-approaching closing date of the project (currently June 30, 2025). Ministry of Water Resources should to expedite the submission and approval of revised PC-1 to ensure signing and effectiveness of the negotiated loan and financing agreements well before the existing closing date and to ensue availability of the Additional Financing for implementation of the project activities.

The sources said, World Bank has observed that work on 4,320 MW Dasu Hydropower Project has considerably slowed down, due to restrictions on the ground-transportation of international workers and experts from Islamabad to Dasu and shortage of armored vehicles for their movement within the project areas.

A World Bank Mission was in Pakistan from September 2-13, 2024 for attestations of the facts of multibillion-dollar project.

The Mission also held meetings with authorities of Water and Power Development Authority (Wapda), and the National Transmission and Despatch Company (NTDC) for the support extended to the World Bank’s implementation support for Dasu Hydropower Stage I Project (DHP-I). DHP-I includes Dasu Hydropower Project (DHP) and Dasu Transmission Line (DTL).

The World Bank’s Board of Executive Directors approved $1 billion as the second additional financing for DHP-I on June 10, 2024, with IDA credits 7563-PK, 7564-PK, and IBRD Loan 9680-PK. The Bank had requested EAD to complete the signing of the IDA credit and IBRD loan agreements at the earliest so that the Project’s financing costs are optimized by using the concessional Shorter Maturity Loan in IDA 7563-PK.

The Bank has requested the government to take security measures to ensure the safety and security of the project personnel and to facilitate necessary movement of international workers and experts to improve the construction progress.

The mission observed that works in DHP have considerably slowed down, due to restrictions on the ground-transportation of international workers and experts from Islamabad to Dasu and requirement of armored vehicles for their movement within the project areas.

The Mission maintained that in DHP the concreting of the integrated coffer dam is the next major milestone. It is likely to start in the low-flow season of 2025 (ie, August/September 2025) given the slower progress of works since March 2024 and delay in availability of power from the 132 kilovolt (kV) transmission line, which is still under construction. To achieve this milestone and complete the preparatory works in DHP, well-coordinated support from the federal, provincial, and local governments to the Project and Wapda is necessary.

The mission appreciated the support from Commissioner Hazara in monitoring these disruptions in the project areas.

The DC Dasu, District Police Office and Wapda, need to ensure that contractors’ works are uninterrupted; and (iii) coordinated support from the federal government, Khyber Pakhtunkhwa provincial government, and the district administrations of Lower Kohistan, Kolai Pallas, and Upper Kohistan is necessary to stop further delays of the installation of this transmission line, which will supply power to the crushing and batching plants for concreting the integrated coffer dam and the main dam.

Copyright Business Recorder, 2024

Comments

Comments are closed.

KU Dec 26, 2024 08:33am
Take your time, a country in energy-distress can afford these delays? And the only time we hear news n updates on slow work on dam project is through WB or IMF, while local media hides it. Tragic.
thumb_up Recommended (0)
KhanRA Dec 26, 2024 11:11am
Do we need this now? Pakistans transition to solar is one of the worlds fastest, and is causing reduced demand from the national grid
thumb_up Recommended (0)
Saleem Dec 26, 2024 12:34pm
The government should not construct this project severe excess generation capacity it will only add to more capacity payments. cheaper renwable energy available through solar and wind
thumb_up Recommended (0)
Taimoor Dec 26, 2024 01:53pm
@Saleem, Illiterate person hydropower is cheapest and one of the most clean form of Energy. Secondly, no solar or wind based grid can produce close to 4000 MW of energy. Countries don't run on solar
thumb_up Recommended (0)
Pakistani Dec 26, 2024 02:35pm
@KhanRA, we needs these as people are not yet off-grid due to cost of high capacity batteries. We should get rid of fuel powered plants though.
thumb_up Recommended (0)
NAVEED Dec 27, 2024 08:38am
Those who miss the closing date of the project and wait for revision cost time and money to the nation. Such people must be punished and should never allowed to be part of any other development projt
thumb_up Recommended (0)