AIRLINK 212.82 Increased By ▲ 3.27 (1.56%)
BOP 10.25 Decreased By ▼ -0.21 (-2.01%)
CNERGY 7.00 Decreased By ▼ -0.35 (-4.76%)
FCCL 33.47 Decreased By ▼ -0.92 (-2.68%)
FFL 17.64 Decreased By ▼ -0.41 (-2.27%)
FLYNG 21.82 Decreased By ▼ -1.10 (-4.8%)
HUBC 129.11 Decreased By ▼ -3.38 (-2.55%)
HUMNL 13.86 Decreased By ▼ -0.28 (-1.98%)
KEL 4.86 Decreased By ▼ -0.17 (-3.38%)
KOSM 6.93 Decreased By ▼ -0.14 (-1.98%)
MLCF 43.63 Decreased By ▼ -1.57 (-3.47%)
OGDC 212.95 Decreased By ▼ -5.43 (-2.49%)
PACE 7.22 Decreased By ▼ -0.36 (-4.75%)
PAEL 41.17 Decreased By ▼ -0.53 (-1.27%)
PIAHCLA 16.83 Decreased By ▼ -0.47 (-2.72%)
PIBTL 8.63 Increased By ▲ 0.08 (0.94%)
POWERPS 12.50 No Change ▼ 0.00 (0%)
PPL 183.03 Decreased By ▼ -6.00 (-3.17%)
PRL 39.63 Decreased By ▼ -2.70 (-6.38%)
PTC 24.73 Decreased By ▼ -0.44 (-1.75%)
SEARL 98.01 Decreased By ▼ -5.95 (-5.72%)
SILK 1.01 Decreased By ▼ -0.02 (-1.94%)
SSGC 41.73 Increased By ▲ 2.49 (6.35%)
SYM 18.86 Decreased By ▼ -0.30 (-1.57%)
TELE 9.00 Decreased By ▼ -0.24 (-2.6%)
TPLP 12.40 Decreased By ▼ -0.70 (-5.34%)
TRG 65.68 Decreased By ▼ -3.50 (-5.06%)
WAVESAPP 10.98 Increased By ▲ 0.26 (2.43%)
WTL 1.79 Increased By ▲ 0.08 (4.68%)
YOUW 4.03 Decreased By ▼ -0.11 (-2.66%)
BR100 11,866 Decreased By -213.1 (-1.76%)
BR30 35,697 Decreased By -905.3 (-2.47%)
KSE100 114,148 Decreased By -1904.2 (-1.64%)
KSE30 35,952 Decreased By -625.5 (-1.71%)

The power sector continues to battle inefficiencies, and the numbers tell a grim story. Two indicators—Part Load Adjustment Charges (PLAC) and Non-Project Missed Volume (NPMV)—highlight the financial strain of suboptimal operations, both on the sector and end-consumers.

PLAC, triggered when power plants operate below their full load capacity, has seen a steep rise over the past few years. From Rs18.7 billion in FY20 and FY21, the cost surged to an eye-watering Rs55.7 billion in FY24. This escalation stems from inefficiencies inherent in underutilized generation capacity, compounded by rigid Power Purchase Agreements (PPAs) that allow plants to claim these charges.

The burden is directly passed onto consumers through monthly Fuel Price Adjustments (FPA), making electricity more expensive for households and businesses alike. The current trajectory suggests PLAC costs will only grow as PPAs with the CPPA-G are finalized, underscoring the need for urgent intervention. Optimizing operations of baseload plants, particularly coal and efficient thermal units with steam turbines, is a logical step forward.

These plants operate best near full capacity, unlike hydro and gas turbines, which are better suited for handling short-term peak demand. Furthermore, adopting Time-of-Use (TOU) tariff structures could flatten demand curves and reduce PLAC incidence. Efficient TOU tariffs would better align generation with consumption patterns, cutting down on part load operations. However, balancing grid stability with fair compensation for underutilized plants remains an act that demands innovative policy solutions.

While PLAC captures inefficiencies within power plants, NPMV represents lost potential due to grid constraints. In FY24, NPMV energy surged to 1,337 GWh, translating to a financial impact of Rs39.5 billion—a staggering jump from just Rs11.8 billion in FY23. The trend reflects a worrying paradox - even as Pakistan invests heavily in renewable energy, inadequate transmission infrastructure, and poor grid connectivity prevent the effective evacuation of power from renewable plants, especially wind farms. NPMV payments effectively penalize consumers for energy that could have been generated but wasn’t, further straining electricity tariffs.

This inefficiency undermines the economic viability of renewable energy projects, dampening investor confidence in a sector critical for long-term energy sustainability. Addressing this issue requires decisive action. Grid constraints must be resolved, and system operations improved to ensure renewable projects deliver their promised benefits. Enhancing grid connectivity for wind and other renewable plants can significantly reduce NPMV, making the case for a cost-effective and reliable energy source.

The combined financial impact of PLAC and NPMV highlights systemic inefficiencies that demand more than cosmetic fixes. On the PLAC front, optimizing base load plant operations and implementing TOU tariffs could curb rising costs. For NPMV, strengthening grid infrastructure and improving operational readiness are non-negotiable.

Both challenges point to a larger issue: the lack of alignment between policy, infrastructure, and operational realities. Policymakers and industry stakeholders must act swiftly to address these inefficiencies. The road to a more efficient and sustainable power sector may be long, but tackling PLAC and NPMV head-on is a critical first step.