AGL 40.14 Increased By ▲ 0.14 (0.35%)
AIRLINK 132.30 Increased By ▲ 2.77 (2.14%)
BOP 6.88 Increased By ▲ 0.20 (2.99%)
CNERGY 4.54 Decreased By ▼ -0.09 (-1.94%)
DCL 8.90 Decreased By ▼ -0.04 (-0.45%)
DFML 42.40 Increased By ▲ 0.71 (1.7%)
DGKC 84.00 Increased By ▲ 0.23 (0.27%)
FCCL 32.99 Increased By ▲ 0.22 (0.67%)
FFBL 76.71 Increased By ▲ 1.24 (1.64%)
FFL 12.06 Increased By ▲ 0.59 (5.14%)
HUBC 109.82 Decreased By ▼ -0.73 (-0.66%)
HUMNL 14.38 Decreased By ▼ -0.18 (-1.24%)
KEL 5.49 Increased By ▲ 0.10 (1.86%)
KOSM 8.25 Decreased By ▼ -0.15 (-1.79%)
MLCF 39.22 Decreased By ▼ -0.57 (-1.43%)
NBP 64.75 Increased By ▲ 4.46 (7.4%)
OGDC 198.61 Decreased By ▼ -1.05 (-0.53%)
PAEL 25.75 Decreased By ▼ -0.90 (-3.38%)
PIBTL 7.64 Decreased By ▼ -0.02 (-0.26%)
PPL 158.81 Increased By ▲ 0.89 (0.56%)
PRL 26.17 Decreased By ▼ -0.56 (-2.1%)
PTC 18.24 Decreased By ▼ -0.22 (-1.19%)
SEARL 81.50 Decreased By ▼ -0.94 (-1.14%)
TELE 8.11 Decreased By ▼ -0.20 (-2.41%)
TOMCL 34.40 Decreased By ▼ -0.11 (-0.32%)
TPLP 8.82 Decreased By ▼ -0.24 (-2.65%)
TREET 16.88 Decreased By ▼ -0.59 (-3.38%)
TRG 59.00 Decreased By ▼ -2.32 (-3.78%)
UNITY 27.55 Increased By ▲ 0.12 (0.44%)
WTL 1.40 Increased By ▲ 0.02 (1.45%)
BR100 10,629 Increased By 222.5 (2.14%)
BR30 31,915 Increased By 201.2 (0.63%)
KSE100 98,906 Increased By 1577.4 (1.62%)
KSE30 30,780 Increased By 588 (1.95%)

Mangla Refurbishment Project, which is being implemented by the Pakistan Water and Power Development Authority, will increase the generation capacity of Mangla Hydel Power Station from 1,000 megawatts to 1,310 megawatts, Chairman Zafar Mahmood said in a visit to the Mangla Dam on Friday.
He had a detailed round of the Mangla Hydel Power Station, the dam and the spillway and then of the Mangla reservoir rim at Khaliqabad that also saw the presence of Member (Power) Badr-ul-Munir Murtiza, Mangla Dam General Manager Ghulam Sarwar Memon and other senior officers.
He said, "There is a dire need of injecting low-cost hydroelectric power to the national grid to mitigate electricity shortages and reduce electricity tariff. Therefore, it is imperative that the Mangla Refurbishment project be completed within the stipulated time frame."
In reference to the high flows and the present water level in the Mangla Lake, which is 1236.7 feet, the chairman directed the authorities concerned to take utmost care and strictly follow the criterion jointly devised by all stakeholders for filling the reservoir.
It was reported that the Mangla Refurbishment project would be completed in three phases with approved PC-1 amounting to Rs 52,224.3 million. On completion of the project, the existing installed capacity of Mangla Hydel Power Station will raise by another 310 megawatts with additional energy generation of 1632 million units of electricity per annum.

Copyright Business Recorder, 2015