AIRLINK 202.36 Increased By ▲ 1.12 (0.56%)
BOP 10.16 Increased By ▲ 0.19 (1.91%)
CNERGY 7.18 Increased By ▲ 0.29 (4.21%)
FCCL 37.11 Increased By ▲ 1.75 (4.95%)
FFL 17.20 Increased By ▲ 0.05 (0.29%)
FLYNG 25.66 Increased By ▲ 1.45 (5.99%)
HUBC 135.40 Decreased By ▼ -2.79 (-2.02%)
HUMNL 14.11 Increased By ▲ 0.04 (0.28%)
KEL 4.85 Decreased By ▼ -0.01 (-0.21%)
KOSM 6.69 Increased By ▲ 0.03 (0.45%)
MLCF 46.30 Decreased By ▼ -0.01 (-0.02%)
OGDC 222.70 Increased By ▲ 0.16 (0.07%)
PACE 7.04 Decreased By ▼ -0.02 (-0.28%)
PAEL 42.50 Decreased By ▼ -0.64 (-1.48%)
PIAHCLA 17.05 Increased By ▲ 0.02 (0.12%)
PIBTL 8.60 Increased By ▲ 0.06 (0.7%)
POWER 9.67 Increased By ▲ 0.57 (6.26%)
PPL 188.25 Decreased By ▼ -0.51 (-0.27%)
PRL 42.49 Decreased By ▼ -0.78 (-1.8%)
PTC 25.30 Decreased By ▼ -0.05 (-0.2%)
SEARL 108.70 Decreased By ▼ -1.72 (-1.56%)
SILK 1.02 Decreased By ▼ -0.01 (-0.97%)
SSGC 42.50 Decreased By ▼ -0.14 (-0.33%)
SYM 18.44 Decreased By ▼ -0.13 (-0.7%)
TELE 9.09 Decreased By ▼ -0.03 (-0.33%)
TPLP 13.51 Decreased By ▼ -0.17 (-1.24%)
TRG 67.89 Decreased By ▼ -0.27 (-0.4%)
WAVESAPP 10.35 Increased By ▲ 0.08 (0.78%)
WTL 1.85 Decreased By ▼ -0.02 (-1.07%)
YOUW 4.04 Increased By ▲ 0.03 (0.75%)
BR100 12,257 Increased By 37 (0.3%)
BR30 37,254 Decreased By -63.3 (-0.17%)
KSE100 116,056 Increased By 211 (0.18%)
KSE30 36,565 Increased By 88.6 (0.24%)

The failure on the part of Federal Ministry of Communication and Karachi Infrastructure Development Company Limited (KIDCL) to revise PC-1 is causing delay in the approval of Rs 500 million worth road infrastructure project in Karachi.
The project includes construction of 1.5 kms road from Malir Bund from Dadabhoy Town/Expressway up to limits of PNS Mehran, District East Karachi and construction of 10 kms long road from Dumlotte Wells up to link road adjacent to Education City, District Malir Karachi.
The project has been planned to be financed from Public Sector Development Programme (PSDP) under Karachi Package. Its original PC-1 was approved in May, last year with the condition to rationalize the cost.
Ministry of Communication is the sponsoring agency of the project whereas KIDCL is the executing agency with Karachi Development Authority (KDA) and Malir Development Authority (MDA) as the responsible agencies for operation and maintenance after the completion of the project.
According to officials documents, the said project was considered by the CDWP in its meeting wherein CDWP approved the project at a cost to be rationalized by Member (Infrastructure &Road Construction) and Sr. Chief (Transport &Communication) of Planning Commission in consultation with the Government of Sindh/KIDCL to avoid any duplication of scope with any scheme of local/provincial government v in fifteen days.
In compliance of the above CDWP decision, Post CDWP meeting under the Chairmanship of Member (I&RC), Planning Commission was held on 20.08.2018.
After detail deliberations, Post CDWP Committee recommended that the sponsoring/executing Agency will conduct proper site surveys to, include soil investigation and traffic survey/ESAL calculation.
After conducting the above, a PC-1 based on proper design of the pavement along with firmed-up cost will be submitted in Ministry of Planning, Development & Reform to carryout cost rationalization exercise as per CDWP decision. Present PC-1 would be returned to Sponsors, the meeting recommended.
After issuance of the Post CDWP minutes, compliance of the recommendations by the Post CDWP Committee was not received from the sponsoring/executing Agency.
The document showed that a reminder was issued to KIDCL to submit an amended PC-1 in compliance with the Post CDWP Committee recommendations. However no response received from the sponsoring/executing Agency in this regard, document indicated. The last meeting of CDWP held last week returned the project without approval for non-compliance of the recommendations.