AGL 37.99 Decreased By ▼ -0.03 (-0.08%)
AIRLINK 215.53 Increased By ▲ 18.17 (9.21%)
BOP 9.80 Increased By ▲ 0.26 (2.73%)
CNERGY 6.79 Increased By ▲ 0.88 (14.89%)
DCL 9.17 Increased By ▲ 0.35 (3.97%)
DFML 38.96 Increased By ▲ 3.22 (9.01%)
DGKC 100.25 Increased By ▲ 3.39 (3.5%)
FCCL 36.70 Increased By ▲ 1.45 (4.11%)
FFBL 88.94 No Change ▼ 0.00 (0%)
FFL 14.49 Increased By ▲ 1.32 (10.02%)
HUBC 134.13 Increased By ▲ 6.58 (5.16%)
HUMNL 13.63 Increased By ▲ 0.13 (0.96%)
KEL 5.69 Increased By ▲ 0.37 (6.95%)
KOSM 7.32 Increased By ▲ 0.32 (4.57%)
MLCF 45.87 Increased By ▲ 1.17 (2.62%)
NBP 61.28 Decreased By ▼ -0.14 (-0.23%)
OGDC 232.59 Increased By ▲ 17.92 (8.35%)
PAEL 40.73 Increased By ▲ 1.94 (5%)
PIBTL 8.58 Increased By ▲ 0.33 (4%)
PPL 203.34 Increased By ▲ 10.26 (5.31%)
PRL 40.81 Increased By ▲ 2.15 (5.56%)
PTC 28.31 Increased By ▲ 2.51 (9.73%)
SEARL 108.51 Increased By ▲ 4.91 (4.74%)
TELE 8.74 Increased By ▲ 0.44 (5.3%)
TOMCL 35.83 Increased By ▲ 0.83 (2.37%)
TPLP 13.84 Increased By ▲ 0.54 (4.06%)
TREET 24.38 Increased By ▲ 2.22 (10.02%)
TRG 61.15 Increased By ▲ 5.56 (10%)
UNITY 34.84 Increased By ▲ 1.87 (5.67%)
WTL 1.72 Increased By ▲ 0.12 (7.5%)
BR100 12,244 Increased By 517.6 (4.41%)
BR30 38,419 Increased By 2042.6 (5.62%)
KSE100 113,924 Increased By 4411.3 (4.03%)
KSE30 36,044 Increased By 1530.5 (4.43%)

Sindh Chief Minister Syed Murad Ali Shah has said he has been working hard to arrange funds and waiting for Nespak report of design verifications on Karachi Bulk Water Supply K-IV project. "I am committed to complete K-IV scheme," he said, presiding over a meeting to review the present status of the project.
The meeting was attended by Minister Local Government Saeed Ghani, Chief Secretary Mumtaz Shah, Secretary Local Government Khalid Hyder Shah, Special Secretary Local Government Niaz Soomro, MD Water Board Asadullah Khan and PD K-IV project Asad Zamin.
The chief minister was told that K-IV was planned for providing 660MDG or 1200 cusecs water to Karachi in three phases. The Phase-I of 260 MGD, Phase-II of another 260 and phase-III of 130 MGD water supply was to be completed between 2022 and 2026.
The phase-I contract was awarded to FWO in 2016 for Rs 28.187 billion that was to be completed in packages within a period of 24 months. The package-A of civil work cost Rs 15.254 billion and package-B of electrical and mechanical works was signed for Rs 12.9 billion.
The K-IV is a three-phased schemes of channels or conduits (conveyance system) only to carry water from Keenjhar (lake) to Karachi. In 2015-16 it was realised that even if K-IV phase-I project was completed, it would not give any benefit to Karachiites because there would not be enough electricity to pump and supply water that meant there was no connectivity of bulk channel with distribution network.-PR

Copyright Business Recorder, 2019

Comments

Comments are closed.