AGL 38.02 Increased By ▲ 0.08 (0.21%)
AIRLINK 197.36 Increased By ▲ 3.45 (1.78%)
BOP 9.54 Increased By ▲ 0.22 (2.36%)
CNERGY 5.91 Increased By ▲ 0.07 (1.2%)
DCL 8.82 Increased By ▲ 0.14 (1.61%)
DFML 35.74 Decreased By ▼ -0.72 (-1.97%)
DGKC 96.86 Increased By ▲ 4.32 (4.67%)
FCCL 35.25 Increased By ▲ 1.28 (3.77%)
FFBL 88.94 Increased By ▲ 6.64 (8.07%)
FFL 13.17 Increased By ▲ 0.42 (3.29%)
HUBC 127.55 Increased By ▲ 6.94 (5.75%)
HUMNL 13.50 Decreased By ▼ -0.10 (-0.74%)
KEL 5.32 Increased By ▲ 0.10 (1.92%)
KOSM 7.00 Increased By ▲ 0.48 (7.36%)
MLCF 44.70 Increased By ▲ 2.59 (6.15%)
NBP 61.42 Increased By ▲ 1.61 (2.69%)
OGDC 214.67 Increased By ▲ 3.50 (1.66%)
PAEL 38.79 Increased By ▲ 1.21 (3.22%)
PIBTL 8.25 Increased By ▲ 0.18 (2.23%)
PPL 193.08 Increased By ▲ 2.76 (1.45%)
PRL 38.66 Increased By ▲ 0.49 (1.28%)
PTC 25.80 Increased By ▲ 2.35 (10.02%)
SEARL 103.60 Increased By ▲ 5.66 (5.78%)
TELE 8.30 Increased By ▲ 0.08 (0.97%)
TOMCL 35.00 Decreased By ▼ -0.03 (-0.09%)
TPLP 13.30 Decreased By ▼ -0.25 (-1.85%)
TREET 22.16 Decreased By ▼ -0.57 (-2.51%)
TRG 55.59 Increased By ▲ 2.72 (5.14%)
UNITY 32.97 Increased By ▲ 0.01 (0.03%)
WTL 1.60 Increased By ▲ 0.08 (5.26%)
BR100 11,727 Increased By 342.7 (3.01%)
BR30 36,377 Increased By 1165.1 (3.31%)
KSE100 109,513 Increased By 3238.2 (3.05%)
KSE30 34,513 Increased By 1160.1 (3.48%)
Print Print 2020-02-09

Trans Mountain pipeline cost jumps by two-thirds to C$12.6 billion

The Canadian government-owned Trans Mountain oil pipeline is expected to cost C$12.6 billion ($9.47 billion) to expand, a sharp increase from the previous estimate of C$7.4 billion, the pipeline company's chief executive said on Friday.
Published 09 Feb, 2020 12:00am

The Canadian government-owned Trans Mountain oil pipeline is expected to cost C$12.6 billion ($9.47 billion) to expand, a sharp increase from the previous estimate of C$7.4 billion, the pipeline company's chief executive said on Friday.

Trans Mountain Corporation CEO Ian Anderson said the increase was due to court and regulatory delays, rising costs of steel, land, labor and security, and accommodations for indigenous groups who had raised concerns. The company decided to use thicker steel than it had previously planned for sensitive areas such as water crossings and changed its construction techniques to protect places that may have indigenous artifacts.

"As we moved on, it gets costlier and costlier," Anderson said on a conference call. "Time is money, market conditions have changed."

Even so, the expansion will be profitable from the first day it operates, he said. Its in-service date is now expected for December 2022, delayed from the previous estimate of the third quarter of that year.

The project will twin a 67-year-old pipeline and nearly triple capacity to 890,000 barrels per day moving from Alberta to a Pacific coast port near Vancouver.

Copyright Reuters, 2020