Under the Agreement, the payment of overdue receivables is an integral part of the Agreement and the payment mechanism envisaged is two instalments, with 40% of the overdue receivables payable within 30 business days of signing the Agreement.
Under the Agreement, at the request of the Government of Pakistan, in the larger national interest and sectoral sustainability, the future O&M savings and heat rate efficiency, shall be shared by the Parties.
The adjustments increases of Rs.0.2925/kWh and Rs.0.7696/kWh for the months of October 2020 and November 2020 respectively will be applicable to all the consumer categories except lifeline consumers of all the XWDISCOs, stated NEPRA.
As per media reports, the National Electric Power Regulatory Authority (NEPRA) had requested the Central Power Purchasing Agency (CPPA) to increase the price of electricity by Rs 1.52.